Skip to playerSkip to main content
  • 1 year ago
The Finance Minister rubbishes claims made by the Opposition Leader as it relates to the ANR Robinson Airport Terminal Expansion project.
Kamla Persad-Bissessar has stated that the cost overrun so far amounts to over 400 million dollars. Mr Imbert says any cost overrun will be capped at 14 million TT dollar.
Transcript
00:00Finance Minister Colm Embert whose ministry is funding the new terminal
00:04building at the A&R Robinson Airport in Tobago says the opposition leader is
00:08peddling lies relative to cost overruns and its safety. He however admits to a
00:14delay. As of today the original construction contract sum of US $128.7
00:23million has been exceeded by US $2.5 million or 2%. The project is being
00:32built to the highest international standards and appropriate building codes
00:38for an airport. There is no cost overrun of 462 million and the project is behind
00:45schedule because of COVID-19. The Finance Minister describes progress on the
00:52project over the past nine months as remarkable with the planned construction
00:56testing and handover on schedule for March 2025 dismissing the opposition
01:02leaders claim that the date would not be met. At which point the Airports
01:06Authority can commence operational fit-out training and readiness to
01:12support the planned go-live date of July 2025 in accordance with their schedule
01:18that is the Airports Authority schedule. The foundation and superstructure of the
01:23terminal building are safe and the entire project including the foundation
01:28and superstructure is being built in accordance with the appropriate
01:32international standards and building codes. Minister Embert refused to verify
01:37or acknowledge the Mark McDonald Oakley's report circulated by the
01:41opposition though he suggested it may have been dated. I have no idea what is
01:46being circulated but what I can tell you is that both Mark McDonald and
01:50Gleads have reported to the Ministry of Finance that the project is being built
01:56in accordance with the highest international standards. And while
02:00rubbishing suggestions made by the opposition leader that SAP a contractor
02:04was terminated for their unwillingness to rubber-stamp poor work Minister
02:08Embert said their contract was simply not renewed. Nonsense. Absolute nonsense.
02:16There was no request made of any consultant to rubber-stamp anything. In
02:21relation to the variation sought by the main contractor the Finance Minister
02:26says the amount agreed to by NITCO and its consultants is 14 million TT dollars
02:31hence the overrun of 2.5 million US. But Minister Embert said the contractor may
02:37opt to make other claims. The process is that the the employer and the
02:46project engineer will look at it and determine what they believe the
02:50contractor is entitled to and if the contractor is not happy with that it
02:54will then go through the dispute resolution process perhaps ending up in
02:58arbitration or litigation as the case may be. We haven't reached there yet.
03:02Right now the contractors made claims and the panel of consultants have
03:08concluded that they should pay the contractor 14 million dollars which is
03:132.5 over the provided amount of 11.5 million dollars. He does not agree as
03:18suggested by the opposition leader that possible arbitration or legal action
03:23could result in any delays. The contractor is being very cooperative and
03:29the contractor is working with us and you would have heard a word I used
03:34inside of here called remarkable. If anybody who's been visiting to be over
03:40the last year or so and you looked at what the airport looked like the project
03:46looked like in January and yesterday the progress over the last nine months has
03:52been absolutely remarkable. We have no issues with the contractor. The
03:57contractor is working with us and is pushing hard. We asked the minister if
04:02he was pleased with NEDCO's performance which came in for criticism in the
04:06report circulated by the opposition. Well it's a complicated project and I am
04:15happy that we are looking towards a completion in March and as I said there's
04:19been remarkable progress over the last nine months. Well I just answered you.
04:25There has been remarkable progress over the last nine months. The word
04:29remarkable means something good I think. Imbed gave the project a thumbs up as he
04:36said it marks technological advancement for Tobago. We are now going to have
04:40loading bridges for aircraft for the first time in Tobago to accept
04:45international aircraft 777 aircraft and so on jumbo jets and so on and this to
04:52me is taking aviation in Tobago and tourism in Tobago to into the 21st
04:58century and I am happy to be part of this gift to the nation. Consultants
05:05Martin McDonald and Gleads have been paid a total of six hundred and twenty
05:09one thousand US dollars via technical non-reimbursable agreements with CAF
05:14Development Bank of Latin America and the Caribbean.
05:18Urvashi Tewari, Rupanarayan TV6 News
Comments