The Public Utilies Minister says electrical work was completed yesterday at the Caroni Water Treatment Plant which was shutdown for planned maintenance that is schedule to end at midday tomorrow.

But the Minister says today's rainy weather posed a challenge at one WASA booster station.

He says additional resources have been deployed there to ensure the area it serves will not suffer any undue delays in their water supply...when the Plant at Caroni is restarted.

Juhel Browne reports.
Transcript
00:00This Karani Water Treatment Plant is the largest plant in the entire Caribbean region,
00:05producing 75 million gallons of water, working 24-7.
00:11Machines and pumps working 24-7.
00:14Public Utilities Minister Marvin Gonzalez, as he spoke with the media on Saturday,
00:19with regard to newspaper articles about what the Water and Sewerage Authority says
00:24is the planned shutdown of the Karani Water Treatment Plant for maintenance from midday on Friday.
00:31Some 500,000 Wasser customers are affected.
00:36If you go and you interview 10 persons or 20 persons or 15 persons,
00:42I don't regard that to be the general sentiment of people.
00:46I don't regard that because outside of that shutdown,
00:50would those 20 people or 10 people that you are reporting on complaining about poor service?
00:56Wasser has said the planned shutdown of the Karani Water Treatment Plant
01:00became necessary in order to carry out critical electrical maintenance work at the plant,
01:05as well as ancillary works along the Karani North and South Transmission Pipeline Network.
01:11However, during his visit to the El Securo Booster Station on a rainy Saturday morning,
01:17Minister Gonzalez said there was a challenge.
01:20So far, everything is proceeding ahead of schedule.
01:24We have some challenges because of the weather condition at this particular site in El Securo.
01:29The team has just reported to me that they are putting additional contingency measures
01:34to ensure that we keep on schedule.
01:37Minister Gonzalez said additional equipment will be brought to the El Securo Booster Station.
01:42At the other locations, I'm proud to report to you and the national community
01:46that so far we are ahead of schedule.
01:49The electrical work that was supposed to be done at the Karani Water Treatment Plant was completed yesterday.
01:55So far, things are proceeding well.
01:58The teams are all on site at the various locations,
02:02and they are doing what they are supposed to do.
02:05There are no major hindrances, as I say, save for this particular site as a result of the weather condition.
02:10Wasa said during the maintenance works that began on Friday,
02:13it would implement the redistribution of supply from other water treatment facilities,
02:18ensure capacity storage at critical service reservoirs,
02:22and increased water trucking capacity.
02:25Based on what has been reported to me,
02:28I am cautiously optimistic that the south transmission line,
02:33based on the progress that has been made so far,
02:36the water will return ahead of schedule.
02:38With respect to the north transmission line,
02:40everything depends on the mitigating measures that we are putting in place here and now
02:44to ensure that we remain on schedule for the north transmission line.
02:48Wasa said the interruption in the supply of water to the affected customers
02:53due to the shutdown of the Karani Water Treatment Plant
02:56is scheduled to end on Sunday at 12 noon.
03:01Jule Brown, TV6 News.