Vandalism at a WASA facility in Tabaquite, mechanical and electrical failures affecting water supply in El Socorro, and the continued closure of the Laventille community pool.

Government addressed the issues during urgent questions in the House of Representatives, while also outlining its preparations for the anticipated effects of El Niño.

Category

🗞
News
Transcript
00:00The vandalism at WASA's tabakid substation is being treated as a matter of national security, according to Public Utilities Minister
00:08Barry Padaroff.
00:09WASA and the Ministry of Public Utilities has reached out for specific technical, equipment and manpower support across a few
00:18state agencies.
00:20This is now a matter of national security, and therefore I will not want to say more to compromise our
00:27combined efforts.
00:28He says there was security at the station at that time. Padaroff also addressed mechanical and electrical failures at the
00:36El Socorro station.
00:38WASA has advised me this morning that out of the two pumps that operates out of the El Socorro Booster
00:44Station, one is currently functional, the other should be up by 4 p.m. later today.
00:52In light of that, I can also announce, based on the question posed by my colleague from Lopino, that we
01:00have taken immediate steps right now to ensure that the El Socorro Booster Station starts its refurbishment work.
01:08The Minister says he's also advised WASA to review the water trucking arrangements in affected areas and increase the number
01:15of trucks where necessary to provide relief to customers.
01:18Meanwhile, the Laventil Community Pool remains closed.
01:22There are several structural issues, structural cracks, pool leaks and areas of rooted steel along the portal frames at the
01:30Laventil Community Swimming Pool.
01:31Hence, a comprehensive assessment report has to be undertaken to determine the extent of the repairs and renovations necessary prior
01:39to commencing works at the facility.
01:41Part D, a structural assessment report, along with the other preliminary works, are expected to be undertaken, is fiscal 20
01:50-27.
01:51And with the country preparing for the potential effects of El Nino, government says an inter-ministerial committee has been
01:59established to develop a national response plan.
02:01The inter-ministerial committee has prepared a national action plan aimed at strengthening national preparedness, protecting vulnerable communities and reducing
02:12the potential effects of drought, water shortages, wildfires and extreme heat.
02:19The plan is to be submitted to Cabinet for approval.