A High Court judge has dismissed a 90-million-dollar claim brought against the Tobago House of Assembly by construction firm Raghunath Singh and Company Limited over a road project completed nearly two decades ago.

Justice Frank Seepersad ruled that the company's claims were filed too late and failed to comply with key provisions of the contract.
Transcript
00:00The Tobago House of Assembly has secured a major legal victory after the High Court dismissed a more than $90
00:07million claim arising out of the construction of the Lance Fomi Charlotteville Road in Tobago.
00:13The lawsuit was brought by Raghunath Singh and Company Limited, which alleged it was owed millions of dollars for variations
00:19to the project, delays, cost overruns, overhead expenses, environmental requirements, retention monies and other works connected to the contract.
00:29Court documents show the project was awarded in 2022 at a cost of approximately $34.7 million and was scheduled
00:37to be completed within 18 months.
00:40Instead, the project was not completed until 2007, roughly three years behind schedule.
00:47The contractor claimed that changing designs, weather conditions, rising costs, additional environmental requirements and other factors significantly increased the cost
00:57of the project.
00:57By the time the matter reached court, the company was seeking just over $90.6 million, including more than $53
01:05million in interest.
01:07But Justice Frank C. Pessard found that the company's legal challenge came far too late.
01:12The judge noted that the final payment certificate under the contract was issued on August 3, 2007.
01:19However, legal proceedings were not filed until November 2022, some 15 years later.
01:25In his ruling, Justice C. Pessard concluded, quote,
01:28The claimant commenced these proceedings in 2022, which is 15 years after the date of issue of Certificate No. 31,
01:36and accordingly, the claimant's claim in contract is statute barred, end quote.
01:41The court also found that many of the claims being advanced had already been rejected years earlier by the project
01:47supervising engineers,
01:49According to the judgment, claims relating to bridgeworks, piling design changes, fluctuations in labor and material costs,
01:58and additional expenses had either been rejected or never properly certified under the contract.
02:04Justice C. Pessard noted, quote,
02:15The judgment was also critical of the company's handling of its final account.
02:23The court found that the contract required the contractor to submit a draft final statement of account
02:29to the supervising engineers within 30 days of the issuance of the provisional acceptance certificate.
02:35Instead, the company submitted what it described as a final account to the THA years later
02:41by passing the contractual certification process altogether.
02:46Justice C. Pessard emphasized, quote,
03:07The THA also argued that it was not the proper party to the claim because the contract was executed
03:13on behalf of the government of Trinidad and Tobago.
03:16However, the judge rejected that argument, finding that the project was undertaken for the benefit of the THA
03:22and fell squarely within its statutory responsibilities for roads and infrastructure on the island.
03:29Despite that finding, the court ultimately concluded that the contractor had failed to establish any legal entitlement
03:35to the millions of dollars being claimed.
03:38In dismissing the action, Justice C. Pessard ruled that the claims were statute-barred,
03:42unsupported by the evidence and contrary to the contractual procedures agreed by the parties
03:48more than 20 years ago.
03:50Arvishita Wari Rupnarein, TV6 News.