Aired (September 6, 2025): Isang flood control project sa Baliwag, Bulacan na nagkakahalaga ng mahigit ₱55 milyon at idineklarang tapos na noong Agosto 2025, hindi matagpuan! Ang buong ulat, panoorin sa video. #ReportersNotebook #FloodControlProjects

Category

🎈
Fun
Transcript
00:00.
00:02Sa Bulacan matatagpuan ang pinakamaraming flood control projects
00:17na ipinatupad ng Department of Public Works and Highways o DPWH.
00:22Ayon sa pagsasaliksik ng GMA Integrated News Research,
00:30mula July 2022 hanggang May 2025,
00:34nagtayo ng 668 na flood control projects sa iba't ibang bahagi ng probinsya.
00:41Ang kabu ang halaga nito, 43.7 billion pesos.
00:46Sa official website ng Sumbong sa Pangulo,
00:49makikita na ang pinakamahal na flood control projects sa Bulacan
00:54matatagpuan sa tatlong barangay ng Balagtas, Bulacan.
00:58Ang mga barangay ng San Juan, Wawa at Panginay.
01:02Ang halaga nito, mahigit 151.5 million pesos na natapos noong September 30, 2024.
01:11Gamit ang coordinates na nakalagay sa website,
01:14pinuntahan ng reporter's notebook ang proyekto.
01:17Nakalista sa Sumbong sa Pangulo website ang nasa 151 million pesos flood mitigation project
01:24na pakikinabangan dapat ng tatlong barangay.
01:27Kung hahanapin ito base sa coordinates na nakalista sa website,
01:31dito ka sa Barangay Burol itadala.
01:34Pero kahit nalakarin mo hanggang dulo ng kalsadang ito,
01:38wala kang makikita ni isang piraso na flood control project.
01:42Dahil hindi makita ang proyektong nakalagay sa coordinates na nasa website,
01:49binaybay namin ang barangay Panginay.
01:57Makalipas ang sampung minuto, narating namin ang flood control project.
02:01Bumungad sa amin ang hanggang tuhod na baha at maputik na kalsada.
02:10Wawaw Builders, ang isa sa mga construction companies
02:12na nakakuha ng pinakamaraming flood control projects dito sa Bulacan.
02:17Ang pinakamahal na flood control project ng Wawaw Builders
02:20ay matatagpuan sa Bayan ng Balagtas.
02:22Ang project cost ay mahigit 151 million pesos.
02:26Sa dokumentong nakuha ng Reporter's Notebook
02:38mula sa DPWH, Bulacan 1st District Engineering Office,
02:43nakasaad na April 23, 2024,
02:46sinimula ng construction of flood control structures
02:48sa Barangay San Juan, Wawa at Panginay, Balagtas, Bulacan.
02:52238 meters lang ang haba nito
02:55na layunin magprotekta sa mga residenteng nakatira
02:59sa gilid ng Balagtas River laban sa baha.
03:02Pero kapansin-pansin na kasalukuyang ginagawa
03:05ang ilang bahagi ng proyekto sa Barangay Panginay.
03:08Nagkaroon daw ng structural damages ang proyekto
03:11dahil sa mga nagdaang bagyo.
03:14Wala rin daw dagdag gasto sa gobyerno
03:16dahil sakop pa ng warranty ang proyekto.
03:19Sa nakuhan naming dokumento,
03:22Wawaw Builders ang kontraktor
03:24ng flood control project na ito.
03:27Kabilang ang Wawaw Builders
03:28sa top 15 contractors na nakatanggap
03:31ng pinakamaraming flood control project
03:33mula sa DPWH
03:35ayon sa sumbong sa Pangulo website.
03:38Ang halaga nito,
03:39mahigit 4.3 billion pesos.
03:42I now declare this hearing officially open.
03:45Pero sa pagdinig sa Senado Kamakailan,
03:4985 projects ang nakuha ng Wawaw
03:52na nagkakahalaga ng 5.9 billion pesos
03:55ayon kay dating DPWH Secretary Manuel Bonoan.
04:00Magkano ang in-award dito sa Wawaw?
04:03Wawaw Builders
04:05at 85 projects
04:07amounting to 5,971,000,000.
04:11Kabilang ang bayan ng Balagtas
04:14sa mga flood-prone area sa Bulacan.
04:16Pero ang inaasahan nilang proteksyon
04:18laban sa pagbaha,
04:21tila hindi raw naging efektibo.
04:24Sa katunayan,
04:24nito lang nagdaang bagyong Crissing,
04:26Dante at Emong,
04:28lumubog ang ilang lugar sa Balagtas.
04:31Kumusta naman ang baha dito sa lugar niyo, ma'am?
04:38Parang lalo din pong lumala
04:40kaysa yung noon.
04:42Mula nung may ganito,
04:44mas lalong nalala yung tubig dito,
04:46lumaki pa lalo.
04:47Gano'ng kahaalalim?
04:48Dati, hanggang saan lang?
04:50Dato dito lang.
04:51So hanggang dito lang.
04:52Ngayon...
04:52Pag lumaki yung tubig,
04:53hanggang dito na.
04:55Ako maabot na sa halos sa bewang.
04:57Hindi nangyayari dati yan.
04:58Hindi.
04:58Di ba, ang dami na rito.
05:00Flood control project.
05:02Ang mahal pa,
05:03I mean, nagastosan na ng flood control project.
05:06Efective po ba?
05:07Hindi po.
05:08Siguro, kung matapos,
05:09sakaling makokontrol yung tubig.
05:12Kaso parang wala pa.
05:13Ang tagal na po kami nagtitiis.
05:16Ganito pa.
05:17Ganyang kalagayan.
05:19Matagal na rin problema
05:20ang pagtaas ng tubig sa bayan ng Hagonoy,
05:23dulot ng high tide na pinapalala pa
05:25ng pagulan.
05:26Kaya, mga guro at estudyante
05:29ng Hagonoy East Central School
05:31araw-araw nagtitiis
05:33sa mga classroom
05:34na unti-unti
05:35nang pinalulubog
05:37ng tubig.
05:40Anim na mga school buildings.
05:42Yung inabando na na,
05:43hindi na ginagamit.
05:44Sana ay may 20 classrooms ito
05:47na nagagamit pa ng mga estudyante.
05:49Pero,
05:50dahil
05:50hindi na nga nawawala yung tubig pa,
05:52hindi na magamit.
05:53Katunayan,
05:54ang sabi ng mga teacher dito,
05:56kung tayo lalakad
05:57sa mabandang gitna
05:58ng tubig na to,
06:01eaabot yung tubig
06:02hanggang sa bewang.
06:03Lubog din sa tubig
06:05ang parangay
06:05na sa Nagustin.
06:08Natalukoyan po
06:09sa kretasyo
06:10ng mga tao dito sa Hagonoy.
06:12Dito po,
06:12kakaraniwang po talaga
06:13hanggang dito yan.
06:14Kaya lang po kayo,
06:15bumababa na
06:15because of
06:16naglo-low tide na siya
06:17ng time na to.
06:18Pero kanina po,
06:19mataas talaga yung
06:20tubig high tide.
06:21Gaano mataas talaga yung
06:22kanina po dito.
06:29Nadaanan din namin
06:30ng ilang abandonadong gusali
06:32na nalubog na rin
06:33sa baha.
06:41Sa website ng
06:43Sumbong sa Pangulo,
06:44makikita na may ipinatay
06:45yung proyekto rin
06:46sa barangay sa Nagustin
06:47sa Hagonoy
06:47laban sa Pagbaha.
06:50Ang contract cost
06:51o halaga nito,
06:52P77 million pesos.
06:55Sa dokumentong
06:56nakuha ng
06:57reporter's notebook,
06:58nakasaad na sinimula
06:59ng proyekto
07:00noong February 13,
07:012023
07:02at 100%
07:04completed na raw
07:05as of
07:05August 29,
07:062025.
07:09Gamit pa rin
07:09ng coordinates
07:10na nasa website,
07:11pinuntahan namin
07:12ang sinasabing
07:13flood control project.
07:14Nang marating namin
07:21ang itinuturong
07:22lokasyon
07:23ng mapa,
07:24narating namin
07:24ang isang ilog,
07:26pero wala
07:26kaming nakitang
07:27flood control project.
07:32At ang contractor
07:34ng proyekto,
07:35kapareho
07:36ng proyekto
07:36sa Balagtas,
07:38ang
07:38Wawao Builders.
07:39Sa kabilang
07:41bahagi ng ilog,
07:43isang flood control
07:44project
07:44ang nakita
07:45ng aming team.
07:46Gamit ang coordinates
07:47na nasa website,
07:49natuklasan namin
07:50na ito ay ang
07:50Flood Mitigation
07:51Structures
07:52along Barangay
07:52Santa Monica,
07:53Hagonoy,
07:54Bulacan.
07:56Ang halaga
07:56ng proyekto,
07:57mahigit
07:58P77 million pesos,
08:00halos kapareho
08:01ng presyo
08:02ng proyekto
08:03sa San Agustin.
08:05Sa dokumento
08:06mula sa DPWH,
08:07Bulacan,
08:08sinimulan ito
08:09noong February 13,
08:102023
08:11at June
08:122026,
08:132023
08:13naman
08:14ang nadeklarang
08:15completion date.
08:17Pero ang ilan
08:17sa mga proyekto
08:18natuklasang
08:19hindi patapos,
08:21may mga bakal pa
08:22na nakausli
08:23at iniwan
08:24na nakatiwangwang.
08:27Eh,
08:27hindi pa na lang
08:28kompleto kapatik.
08:29Binabaha pa rin.
08:31Wawao Builders din
08:32ang contractor
08:33ng flood control project.
08:36Nagpadala kami
08:36ng sulat
08:37at mensahe
08:38sa Wawao Builders
08:39para kunan sila
08:40ng panic
08:40pero hanggang ngayon
08:41wala silang sagot
08:43sa amin.
08:46Pero sa pagdinig
08:47sa Senado,
08:48dumalo si Mark
08:49Alan Arevalo
08:50ang owner
08:50ng Wawao Builders
08:52nang tanungin siya
08:53tungkol sa mga
08:53sinasabing ghost project
08:55ng kanilang kumpanya.
08:56Familiar ka dito?
08:58Familiar ka,
08:59Mike?
09:00Hindi po yung honor.
09:01Hindi,
09:02dahil,
09:02hindi ka nga talaga
09:03magiging familiar
09:04dahil ghost nga.
09:06Ang nakalagay dyan
09:07sa report,
09:07completed.
09:08Nakakubra ka na.
09:10Nabayaran ka na
09:10ng gobyerno.
09:11Kaya hindi po nakita
09:12yung video,
09:13your honor.
09:13O, talaga
09:14hindi mo makikita
09:15dahil hindi mo
09:15maalam.
09:16Kasi nga ghost.
09:18Your honor,
09:19I invoke my
09:19right against
09:20incrimination,
09:21your honor.
09:21Saka identical
09:23ang presyo ha.
09:2477 million,
09:2577 million,
09:2672 million,
09:2772 million.
09:28Bakit ganun?
09:31Mr. Arevalo,
09:32kung 42 projects ito,
09:3442 plunder cases ito eh.
09:41Nito lang September 4,
09:42nag-inspeksyon
09:43si bagong DPWH
09:44Secretary Vince Dizon
09:46sa isang flood control
09:47project sa Plaridel,
09:48Bulacan
09:49dahil dineklara
09:50ng 100%
09:51completed
09:51kahit na
09:52ongoing pa lang
09:53ang proyekto.
09:55This is
09:56criminal.
09:58Mga hayop
09:59ito mga tao
09:59ito,
09:59hindi tao ito
10:00ito.
10:00I will also
10:02order
10:02the perpetual
10:03lifetime
10:04blacklisting
10:05of Wawao
10:06builders
10:07from DPWH
10:09and all
10:10their
10:10possible
10:11affiliates.
10:13Probinsya ng Bulacan
10:14ang nakakuha
10:15ng pinakamaraming
10:16flood control
10:17projects,
10:18668 projects
10:20na may kabuang
10:21halaga
10:21na mahigit
10:2243 billion
10:23pesos.
10:24Pero ilan
10:25sa mga
10:25proyektong
10:26ito
10:26ay hindi
10:27matagpuan
10:28o ghost
10:28projects.
10:3027 kilometers
10:31mula sa
10:32Hagonoy,
10:33Bulacan,
10:34isa pang
10:34flood control
10:35project
10:35ang itinayo
10:36sa Barangay Piel,
10:37Baliwag City,
10:38Bulacan.
10:40Ang construction
10:40of reinforced
10:41concrete
10:42river wall
10:43sa Purok 4,
10:44Barangay Piel,
10:45Baliwag,
10:45Bulacan.
10:46Ang contract
10:47amount,
10:4755.73
10:49million pesos.
10:50February 25,
10:522025
10:52ang date
10:53of
10:53effectivity
10:54at 100%
10:55completed
10:56na raw ito
10:57as of
10:57August 31,
10:592025.
11:01Pero
11:02ng puntahan,
11:03nawawala rin
11:04ang
11:05proyekto.
11:06Sa dokumento
11:07mula sa
11:07DPWH
11:08Bulacan,
11:09SYMS
11:10Construction
11:11Trading
11:11ang
11:11contractor
11:12ng
11:12project.
11:13Ayon sa
11:14isang
11:14opisyal
11:14ng
11:14barangay,
11:15nakipag-coordinate
11:16pa raw sa
11:17kanilang
11:17barangay
11:17ang
11:17construction
11:18company
11:18para sa
11:19pagtatayuan
11:20ng
11:20barracks
11:21ng
11:21mga
11:21trabahador.
11:22Pero
11:22hindi na
11:23raw sila
11:23bumalik.
11:24As in,
11:25naging
11:25ghost na
11:26rin sila.
11:27Yung
11:27misto
11:28lang
11:28naglaho
11:29na rin.
11:30Kaya
11:30hindi
11:31lang sila
11:31ghost
11:31contractor.
11:32As in,
11:32multok.
11:33Talagang
11:33magugulat
11:34po kami
11:34dahil
11:35sila
11:36nakipag-coordinate
11:37sa
11:37barangay
11:37muna.
11:39Sa
11:39kabuan,
11:40umabot sa
11:4016
11:41flood
11:42control
11:42projects
11:43na
11:43nakuha
11:43ng
11:44SYMS
11:45mula
11:452022
11:46hanggang
11:462025
11:47ang
11:48halaga
11:48mahigit
11:49P931
11:50million
11:51pesos.
11:53Pinadalhan
11:54namin
11:54ng
11:54sulat
11:55ang
11:55SYMS
11:56Construction
11:56Trading
11:57para
11:57kunin
11:58ang
11:58kanilang
11:58pahayag.
11:59Pero
11:59hanggang
11:59ngayon,
12:00wala
12:00silang
12:01sagot
12:01sa
12:01amin.
12:06Pahayag.
12:07Pahayag.
12:08Pahayag.
12:09Pahayag.
12:10Pahayag.