00:00Hello, how are you? How are you doing? Welcome to session number 7, the subject Project
00:20Integrator. This time we're going to work on step number 5, which relates to how to accelerate
00:33The plan, how to accelerate the time it will take you to launch the project. We saw this in the previous session.
00:43We went through steps 1 through 4 and discussed defining the project. We did that through a
00:51methodology known as SMART, where we specifically define what it would consist of
00:57the project we're going to work on. It's important to clarify that this is an example.
01:03Only, but you must be working on the project you've chosen. The next step
01:09What we handled last time was number 2, which consisted of listing the tasks. We did
01:18Through this, through this process, a brainstorming session was held.
01:24Both for yourself and for someone else. You were advised to find someone to help you with this.
01:31brainstorming, which could be someone close to you, or perhaps all at once the people who can
01:37I will be supporting you later in the launch and management of the project you will be working on.
01:47So it's important that you do it that way. Once you already had them related or listed
01:56On Post-it notes, list all the activities and resources you needed or need to complete your project.
02:04For the project, we provided the costs for each of those activities and the time it would take.
02:12the execution of them. But that wasn't all we did. On that occasion we also said
02:22Adding up the total time and total cost, we found that the cost of this project,
02:29In the example we have, it was 83,500 pesos and 80 weeks in total. In your case,
02:37You should already have your figures identified if you ran the process we saw in the session
02:43Previous. But it's important that you have this data well managed because we're going to base our analysis on this.
02:52making definitions and making decisions about it. We also said that another process was,
03:02In addition to estimating the times and costs, we also gave each of these activities a specific order. And we put
03:09a sequential order that we were going to do first and that would be the next activity or resource that we were going to
03:19to be obtaining. So, this order will allow us to have a better
03:28control in how we are going to carry out each of the activities necessary for the project.
03:36And this is where we encounter an important issue. When we define the total amount, the cost, and the time
03:45that will take us, we have to start making decisions about it. For example, in this case we find
03:52It would take us 80 weeks to complete this project. 80 weeks is a long time, really.
04:00We don't recommend taking on projects that take this long. In fact, no longer than three or four months.
04:10At most, perhaps 15 weeks for the full launch of the project.
04:19Because if we give it more time, what will happen is that you'll end up abandoning the project.
04:27You won't be able to do it because the time you'll have to dedicate to it will be quite, quite a lot.
04:35And maybe it's time you don't have. So, let's try to have a project with a shorter launch time.
04:43However, when you get this number of weeks, don't automatically discard the project.
04:49First, we need to run an analysis. First, we need to see if we can accelerate the project.
04:55And that's where we begin with step number 5, which consists precisely of seeing what ways we have to carry out a project more quickly.
05:09We will do this along with drawing a Gantt chart, which is a timeline.
05:15which will help us precisely to put the activities in sequence and see what activities we could be carrying out at the same time.
05:27Another point we'll cover in this session is step number 7, which is obtaining the necessary resources.
05:34And step number 8, which consists of assessing risks and preparing action plans.
05:40Let's move on to step number 5, which is to accelerate the project.
05:44Every project, regardless of the type of project it is, will always consist of three elements, and one cannot be modified without modifying one of the others.
05:56Those elements are time, cost, and quality of scope.
06:01In the project we are looking at as an example, the time is 80 weeks.
06:07In your case, you must have the time already defined there.
06:10The cost came to 83,500 pesos and the quality and scope are related to the project definition.
06:20In this case, at 80 breakfasts.
06:23In other words, my reach is 80 breakfasts per day.
06:26If I want to reduce the time it takes to do it, well, I can't reduce the time, once I've already evaluated all of this: time, cost, quality, and scope.
06:38I cannot reduce the time if I do not make some adjustment to one of these two elements, either in cost or in quality and scope.
06:47Let's see what we can do in this example we're reviewing to reduce the time.
06:54For example, we are saying that we will try not to change the scope, that it will remain at 80 breakfasts,
07:03But we would have to increase the cost.
07:07As?
07:08We could be looking for more people to help us, more volunteers, or even some people who could pay some kind of financial support.
07:20to help us both in finding a location and in finding staff or people who can support us with donations or volunteers, a greater number of volunteers.
07:33The more people involved, the more help we have, the less time it will take to launch the project.
07:39I might need to rent a place that's already set up, and that will allow me to reduce the time, but it will increase the amount of the cost I'll have here.
07:51Or perhaps I have hired someone or I've seen a quote from someone who will do the remodeling and charges me a low price,
08:01But if I pay him more, he can do it in less time.
08:06This might mean that instead of 83,500 pesos my cost will go up to 150,000 and that instead of having a time here for 80 weeks, I can lower it to 40 weeks.
08:21It's one way, but what I find here is that even though I did this, it's still 40 weeks and it feels like too long.
08:31I'll look for other alternatives then.
08:34What else can I do?
08:35What I can do is shift the quality and scope.
08:39Instead of 80 breakfasts, I can say that I will aim to make 30 breakfasts a day.
08:46I must always make sure that the scope doesn't detract too much from what I want to do, or above all, it must continue to be a project that pleases the Lord.
08:57So I can't undervalue it that much.
08:5930 breakfasts could still be considered a reasonable amount.
09:04So if I reduce the scope, the number of breakfasts in this case, that will allow me to lower my costs because I will need less equipment.
09:14fewer volunteers and a smaller venue, for example.
09:19And that will also allow me to put my cost of $83,500, in this case fictitiously, just to put an amount at $50,000 pesos.
09:32Then my cost went down, but the interesting thing is that my time also went down.
09:37Here my time dropped to 30 weeks.
09:40It is still a large or extensive amount, over a long period of time.
09:4630 weeks is a long time.
09:48We were still saying that 15, 16 weeks is the maximum that can be acceptable.
09:54But hey, let's not rule it out just yet.
09:58We need to go to step number 6 where we will graph the activities on a timeline.
10:06And that will allow us to see which activities are overlapping, which activities I can anticipate others,
10:13to see if I can reduce the time even further.
10:17And once I have that, then I can fully launch into the realization of my project with the following steps.
10:27I ask that you please apply this analysis, which we have just done as an example, to the project you have chosen.
10:36so that in the next step we can start working in more detail.
10:44I'll see you in the next video.
10:46See you later.