00:00Hello, how are you? Welcome back to another session on the topic of
00:20How to prepare your work plan for carrying out your project.
00:26As we saw, this process we are using consists of 12 steps, and in the previous session
00:35We were reviewing step number 5, which consists of how we can accelerate the project.
00:43Let's remember that we were talking about the number of weeks or time that the project takes you,
00:49The recommendation is that it should not exceed 15 or 16 weeks. Therefore, in the case we are using as an example,
00:58We found that we have 80 weeks and we need to find a way to reduce the time
01:05so that we can complete the project properly.
01:11We said that the three important pillars we have in any type of project are
01:16project cost, project time, and quality of project scope.
01:21And any change in one of these pillars implies adjusting one of the other two remaining pillars.
01:31So if we want to reduce the time, we would also have to reduce the quality or scope, or increase the costs.
01:41Let's now look at step number 6, which consists of accelerating the plan, but by drawing the GAN diagram.
01:51The GAN diagram will not only help us accelerate the plan,
01:57It serves as a tool that will allow us to maintain very precise control of the project.
02:06Once we have the list of activities, the cost of the activities, and the time required to complete them,
02:14The first part is that we are going to list those activities in the GAN diagram and assign them the completion time.
02:22in such a way that they allow us to accommodate the activities, both those that are dependent on each other,
02:29such as those that are not dependent and that we could be anticipating those activities to also reduce the time.
02:37But it will also allow us, once we have a well-defined plan, with the timelines, activities, and responsible parties,
02:45Keeping track of progress, as we move forward, we will see that it will be very important to monitor the progress of our project.
02:57That is the primary tool we will use to ensure that the project will be successful.
03:06Well, in previous sessions we saw that we have to make the list of activities,
03:13We need to assign a cost to each of the activities and the time required to complete them.
03:19In addition to that, we had to put a sequential order to the activities,
03:25In other words, what was the first activity we were going to carry out, what was the second, the third,
03:30And so on, we would have to give those activities an order.
03:36It is very important that you do not want to skip any of the twelve steps.
03:42You have to use the steps or perform them sequentially.
03:48In other words, the first step is to describe what your project consists of using the SMART methodology.
03:56Second step, list your activities.
03:58Then we have to factor in the time, the cost, the money, the value of the resources, and the time that each activity takes us.
04:10Then give order to each activity, the sequential order.
04:15What we did previously and the analysis we saw helped us understand that the three elements of the project,
04:26cost, time and quality or scope,
04:29They allow us, when we make the Gantt chart,
04:34We already have a very important foundation to be able to make that Gantt chart.
04:39If we want to skip ahead and directly create the Gantt chart,
04:43We're going to get into trouble and it's not going to turn out as it should.
04:47So, having these elements and these steps,
04:51Now then, what I'm going to do here is paint a timeline.
04:56A timeline that I'm painting here in weeks.
04:59You can do this in a spreadsheet or you can do it on a sheet of paper
05:06where you draw a timeline.
05:09Here each number represents a week, each column represents a week.
05:15I'm only charting 30 weeks here.
05:18Because even though there are 80, I know that when I organize my activities,
05:23Since not all activities have to wait for one to finish before another can begin,
05:31Well, they're going to overlap and it will allow me to reduce the number of weeks from 80.
05:39So, here's my timeline,
05:42I have a list of each of my activities in sequential order.
05:46And with the order I gave it here, 1 is local, 2 is kitchen,
05:52Step 3 is to process the permits and so on.
05:56Just as I described the order I gave it here, that's how I'm going to list my activities
06:01and I'm going to specify how many weeks each activity should take.
06:08Later, once I had created my timeline,
06:12Well, I'm always going to be trying to control how much I cost.
06:17But above all, how much time do I have?
06:21We said we were 80 weeks along,
06:23But when we started graphing in Gantt charts,
06:27What we're going to find is that we have a great advantage.
06:32My first task is to find the premises.
06:35I can't send that to the last few weeks.
06:39That's the first thing I have to do.
06:40If it's number 1, then from week 1 to week 10,
06:46I'll tell him that I'm going to focus on getting the place.
06:50What about point 2?
06:51The kitchen.
06:52It's 10 weeks.
06:53I'm not going to graph it from 11 to 20.
06:56Because?
06:57Because even though I have to adapt the kitchen to the premises,
07:01I may have already identified the location
07:05maybe in week 7 or week 8.
07:08And with that, I can start looking for my kitchen suppliers.
07:15I can even see who is going to make donations for the kitchen.
07:19If someone is going to donate any equipment to me,
07:23do the promotion, find donors.
07:26I can start doing that before step number 1 is even finished.
07:30So here I say that the first step took me 10 weeks.
07:35In the next step of the cooking process, I mark it from week 6.
07:39Because I don't have to wait until I finish getting the place.
07:43to start finding someone to donate the kitchen to me
07:47or where to buy the kitchen or whatever I need to buy.
07:50The entire kitchen team.
07:52In the case of permits, and here I also see, sorry,
07:56that the total number of weeks is not 20.
07:58I've been here for 15 weeks.
08:01Regarding permits, well, once I have identified the premises,
08:05I can ask the owner to provide me with the documents
08:09to begin my permit application process.
08:12So here I put that in week 9,
08:148 weeks from 9 to 16.
08:16So here, instead of 28 weeks, I'm at 16 weeks.
08:22And so I continue working and move on to the topic of services.
08:26Gas, water, telephone, and electricity services.
08:31Possibly, once the premises have been located,
08:33I know there are some services that are already available at that location
08:37and I don't have to hire them.
08:38But surely the gas, and how it's going to be something,
08:42Well, not for housing, but for a different issue,
08:46A bit industrial, well, then I have to see what the contracts are
08:50make sure they are suitable so you don't have a problem
08:52that they may subsequently shut me down
08:55or something like that, right?
08:57So from week 9,
08:59I illustrate that those 12 weeks run from week 9 to week 20.
09:03So I'm in week number 20,
09:05instead of considering here that it is 10 plus 10,
09:09plus 8, 28, plus 12, 40 weeks.
09:12I only have 20 weeks here that I'm using.
09:15I start looking for my volunteers from week 9 to week 13.
09:22I've been at it for 20 weeks, the number of weeks doesn't change.
09:25The utensils too, the volunteers are going to help me.
09:28to get the utensils.
09:29So from week 14 to week 16,
09:33They themselves help me and I can take advantage of it
09:35I am counting on your support to obtain those supplies.
09:42I'm still 20 weeks pregnant.
09:45The tables too, once they finish getting the utensils,
09:49I ask for your support in getting the tables.
09:54The ingredients, well, maybe that,
09:58when they start looking for the tables,
10:00They begin to look for the ingredients,
10:02or rather the volunteers,
10:04ingredient donors
10:06that they will be providing me with
10:07everything you need for food preparation.
10:14And one phase has now ended.
10:15I finished one phase by week 22.
10:18I'm going to the other service I was going to manage,
10:22or that I considered important to include,
10:25taking advantage of the fact that the place is open in the afternoons
10:27It was going to be available.
10:29the medical service.
10:31I'll have to wait until I've made good progress.
10:35in this first phase
10:36to begin working on the topic of the doctor.
10:41And here I say, well,
10:42By week 14 it is already more advanced
10:45the whole topic of cooking and food.
10:48And I already have the volunteers.
10:50Okay, now I'm going to start looking.
10:52Once I have the volunteers,
10:53I focus more on searching
10:56Who will support me as a doctor?
10:59And I'll illustrate that over those eight weeks.
11:01from 14 to 21.
11:04The doctor was already there,
11:06Okay, I'm starting to work
11:08with the topic of the doctor's office.
11:10I've been here for 22 weeks.
11:12Yeah?
11:13Up to 22 weeks here.
11:15It's not 80 yet.
11:17So I'm seeing that it will help me.
11:19A lot of graphing to know
11:21or to have a slightly clearer understanding
11:23How many weeks is the project really going to take me?
11:26The consulting room, I mean,
11:28Well, since I have the doctor,
11:29He helps me himself
11:31to set up the office
11:33in what equipment is needed
11:35from 22 to 27.
11:38And the same,
11:40I see here too that the weeks
11:42It's 27 weeks in total.
11:44And the same doctor
11:46It will help me too.
11:47to get the medications.
11:49Or to find someone who will donate to me
11:50medicines.
11:51Because he has to tell me
11:52what type of medications
11:53They will be used.
11:55And well,
11:56I continue here
11:57with the topic of brochures.
11:58I don't have to wait
11:59to finish this whole process
12:01for a start
12:02with the topic of brochures.
12:04I say,
12:05hey,
12:05if I know that
12:06the medicines
12:07I'll have them ready soon.
12:08in week 27,
12:10Well,
12:11I anticipate
12:12five weeks earlier
12:14for a start
12:14with the topic
12:15from the brochures.
12:16in such a way
12:17that I have left
12:18still two weeks
12:19here to promote
12:20and may have
12:22the launch
12:23during the week
12:2528.
12:27My cost
12:28It doesn't change,
12:29It remains
12:2983,500 pesos,
12:32but the total
12:33of weeks
12:34that I have here
12:35It's 27 weeks.
12:37So,
12:37I must
12:40continue evaluating
12:42the topic
12:42in the aspect
12:44to say
12:45if the 27 weeks
12:47They are a time
12:49reasonable
12:50so that I
12:51throw
12:52This project.
12:54As we were saying
12:56previously,
12:56It is not recommended
12:57projects,
12:58at least for this
12:59type of projects,
13:01that go beyond
13:02of
13:0315,
13:0516 weeks.
13:06Because?
13:07Because the topic
13:07This is where
13:08It's a project
13:10unless you
13:13have the time
13:14necessary
13:14full time,
13:17that is to say,
13:17100%
13:18of your time
13:19dedicate it
13:19to this project,
13:20but in many
13:22of the cases
13:23It's not going to be like that.
13:25You have
13:26certain obligations,
13:28responsibilities
13:28at your house,
13:29with your family,
13:31your
13:32so
13:33we recommend
13:34provided they are
13:35more or less
13:3615,
13:3616 weeks
13:37at most.
13:38If it's less time
13:39still,
13:40far better.
13:42But in this case
13:43that we have
13:4427 weeks,
13:46We have to keep going
13:46reviewing
13:47how to reduce
13:48time.
13:50So,
13:51we need to see
13:52the three elements
13:53of the projects.
13:55Remember that it is
13:56time,
13:57is the cost
13:58of the project
13:59and that is the scope
14:00and quality
14:01of the project.
14:02so,
14:04in this case
14:05Specifically,
14:06For example,
14:07what we are going to see
14:08in the next session
14:10or in the following video
14:11rather,
14:13That's how I can change
14:15or adjust
14:17now yes
14:18some of the elements
14:21of the project.
14:21in this case,
14:23we're going to reduce
14:24the amount
14:25breakfasts
14:27that we're going
14:28to drive.
14:29See you
14:30in the next
14:31session
14:33or video,
14:35But I ask you
14:37much that
14:37graphics
14:38this that we are
14:39doing,
14:40do it yourself
14:41for your project
14:41in order to have
14:42a good step forward.
14:43See you later.
14:44Thank you!