00:00Venezuela's Acting President Delsi Rodriguez announced the restoration of the electricity grid following the double earthquake that struck the country,
00:07while calling for precautions in anticipation of the arrival of the Super El Niño.
00:11Rodriguez reported that 50% of the capacity of the Thermo Carabobo power plant, which was affected by the double
00:18earthquake on June 24, has been restored.
00:20The Acting President explained that this progress is key to stabilizing the power grid between the center and the west
00:26of the country,
00:27and announced that full restoration will be completed in the coming weeks.
00:31Also, she ordered a series of preventive plans in anticipation of the arrival of the El Niño climatic phenomenon,
00:38emphasizing that measures such as fire prevention, monitoring of reservoirs, and preservation of watersheds will be implemented.
00:45Finally, she called for national unity urging people to protect nature and use resources wisely.
00:57We have recovered 300 megawatts of the 600 megawatts that the Carabobo thermal power plant was generating,
01:05which is very important because the loss of the Carabobo plant caused instability in the national power grid.
01:12Thermal power plants not only generate electricity, but also serve as a power balancer for the entire system,
01:20especially for the connection between the central and western parts of the country.
01:26The fluctuations we have experienced in recent hours and days are directly related to the significant loss of those 600
01:32megawatts.
01:34And today, I am pleased to say that we have already recovered 50% of that capacity and will be
01:40on track for full recovery in the coming weeks.