00:00DPWH Secretary Vince Dizon inspected several bridge, dike, and roads in Pampanga today.
00:07This follows the directive of President Fernand R. Marcos Jr. to immediately address long-delayed projects to ensure that they can be utilized by the public.
00:16Bernard Ferrer reports.
00:20Eight years nang nakating ito.
00:22This is how long the construction of the new Sanugusan Bridge in Arayat, Pampanga was neglected.
00:26The project was delayed four years due to the lack of funding.
00:29However, the Department of Public Works and Highways, or DPWH, will allocate 75 billion pesos from its savings to resume and complete the project.
00:37This move is in response to the directive of President Fernand R. Marcos Jr. to finish long-neglected projects so they can immediately benefit the public.
00:45Nung nag-usap kami ni PBBM, nung start ng year, yun ang kabigin-biginan niya.
00:52Lahat ng unfinished, tapusin na natin.
00:55And ito, perfect example ito, ng unfinished bridge, pero maraming ganito all over the country.
01:03The local government of Marayat also expressed his gratitude for the swift action of the administration, nothing that the old bridge poses risk to motorists and residents.
01:11Malaking bagay. Ito pag natapos tong tulay na to, maraming makikinabang at kami medyo maging mapapanatag po ang aming loob.
01:19The new San Agustin Bridge is part of the national road and serves as a major route for motorists traveling to Nueva Ecija, particularly to Gapan and Cabiao, especially for the transport of goods.
01:30The project also includes improvement of the right-of-way.
01:33Construction is expected to be completed within the year.
01:36Secretary Dyson also conducted an inspection of the Arnedo Dyke in Barangay Kupang, where a portion of the dyke collapsed during the onslaught of Taipun Uon.
01:43According to the Secretary, two immediate measures will be undertaken.
01:47The construction of temporary protective structures and the creation of a cut-off channel, while permanent solution is being finalized.
01:54The dyke is part of the Pampanga River Flood Management Master Plan, making it crucial to resolve the issue to prevent adverse effects on nearby communities.
02:01Kailangan mabilis yung aksyon natin dito. Kasi buhay ang pinag-uusapan dito, hindi lang sirang infrastructure ang pinag-uusapan natin dito.
02:11Pag ito nasira, pumasok ang tubig dun, tao yan. May mga posibing mamatay dyan, may mga bahay dyan, masisira. So hindi natin pwedeng payagan yun.
02:21Meanwhile, Secretary Dyson also inspected the damaged Apalit section of Bacarthur Highway and Apalit-Macabebe Road in Pampanga, which have caused inconvenience and heavy traffic for several years.
02:32The Secretary ordered the immediate repair of these projects before the onset of the rainy season.
02:36Bernard Ferrer from the National TV Network for new and better full piece.
02:40Thank you very much.