00:00The DPWH, MMDA, and DOTR have laid out a significantly revised plan for the EDSA rehab project,
00:06drastically cutting the timetable from two years down to just eight months with a slashed estimated cost.
00:12Full details on the two phases of the project and the updated schedule in this Gav Villegas report.
00:20The Department of Public Works and Highways, the Metropolitan Manila Development Authority,
00:25and the Department of Transportation has laid out the new plan for the rehabilitation of EDSA.
00:30Instead of two years, the EDSA rehab timetable will be only eight months.
00:36The rehab will be divided into two phases.
00:39The first phase covers from Ross Boulevard in Pasay City to Orense Street in Makati City,
00:45and the second phase covers the rest of EDSA.
00:47From 11 p.m. of December 24 to 4 a.m. of January 5, 2026,
00:53the DPWH will be working 24-7 for re-blocking works in asphalt overlay of busway lanes.
01:01From January 5 to May 31, 2026,
01:05from 10 p.m. to 4 a.m. every Monday to Friday,
01:08asphalt laying will be conducted lane by lane on northbound and southbound.
01:12And every Friday to Sunday, DPWH will also conduct re-blocking and laying asphalt on one lane
01:19each of the northbound and southbound lanes.
01:22With a new version of the EDSA rehab plan,
01:25instead of the estimated cost of 17 billion pesos for the EDSA rehab,
01:30the expected cost for it will be only 8 billion pesos.
01:33According to DPWH Secretary Vince Dizon,
01:36the department will apply a new type of asphalt used in Japan for the rehabilitation of EDSA.
01:42We will be using stone mastic asphalt technology.
01:47This has, itong gagamitin sa EDSA,
01:49I don't think it has been used on our national roads yet,
01:53no, itong technology nito.
01:55Makikita nyo ito mostly sa Japan.
01:57Kung makikita nyo yung mga asfalto sa Japan,
02:00ito yung gagamitin natin teknolohiya.
02:03Dahil hindi na nga tayo mag-re-block ng lahat,
02:06kailangan natin asfaltong matibay.
02:09Hindi yung asfalto, isang ulan lang,
02:10eh, nasisira na.
02:13Daanan na ng tubig, nasisira na.
02:15Ito mas matibay and mas madaling i-maintain.
02:20Mas mahaba ang maintenance life nung asfaltong to.
02:25The Department of Transportation assured the fleet of bus units on the EDSA busway
02:30is enough and will also start the rollout of pre-dallion trains by Christmas.
02:36We'll make sure na kahit paano ma-mitigate yung epekto ng trafico sa EDSA.
02:41Mga kasiguro po kayo na yung ating MRT3 at busway,
02:45parati po nga dyan kahit na mayroong EDSA rehab.
02:48The MMDA also said there will be no changes to the number coding scheme
02:53even though the EDSA rehab has begun.
02:55Ang pagsasara lang ng karasada will happen December 24 to January 5,
03:02which is sa experience namin, sa datos namin,
03:06kakaunti talaga ang sasakyan sa buong Metro Manila.
03:10Maybe because siguro 70% ng population ng Metro Manila
03:15either nasa abroad or nasa probinsya.
03:18Motorists have a positive view of EDSA after rehab.
03:22Malaking ginawa, yun ang magiging kalalabasang magandang malaking ginawa na pag natapos.
03:31Magginawa talaga kung maayos talaga nila yung mga lubak-lubak na yan kung tutusin.
03:34Pero yun nga, magtiis muna tayo sa air-raps sa trafic.
03:37Pero kailang magtiis talaga?
03:39So kapaganda na yung natin yung mga karasada pa
03:43para mas maayos yung darin ng trafico.
03:45Gab Villegas from the National TV Network for New and Better Philippines.