00:00The LRT3 line will be launched after testing and commissioning have been completed in the
00:06middle of next month, says Prasarana Malaysia Berhar CEO Amir Hamdan.
00:12Amir say that the current phase includes trial runs, fault-free runs, and trial operations.
00:30Patrick Huang, LRT3 project director from Satya Utama LRT3 Sundrian Berhar said the company
00:48began the FFR trial on August 26.
00:52Under regulations, he said that a golden train must complete 4,000 km without error, five
00:57trains must complete 3,000 km and the remaining 18 trains 2,500 km each without any glitches.
01:04Huang say 33 issues had been identified during testing, mostly technical problems that could
01:29be fixed by your software patches.