Berwick's £35m hospital build faces major rework after construction failures
The unfinished hospital has left local residents frustrated, while the NHS trust says the project must be put right. Find out what has to be removed, what happens next and how much the work could cost.
#Berwick #Northumberland #NHS #HospitalBuilding #NorthEastNews

Category

🗞
News
Transcript
00:00Work on Berwick's £35 million community hospital will have to be redone after inspections found
00:07construction was not up to standard. Northumbria Healthcare NHS Trust says most of the work
00:13completed so far must be removed, including pipework, electrical systems and parts of the
00:19outside facade. The main structural steelwork will remain. The original contractor, Merritt,
00:25went into administration in late 2025. New contractor Robertson has been assessing the
00:31site, but the additional cost of putting things right is not yet known. The Trust says it has
00:36confidence in Robertson and remains in contact with residents. A public information session
00:41is planned at Berwick Town Hall in December.