Locals bordering Canberra are sick of waiting for the New South Wales government to duplicate the Barton Highway after another fatality this week. A 78-year-old man was the second person to die driving on the highway in only a month when he crashed with a truck on Tuesday.

Category

📺
TV
Transcript
00:00Murram Bateman residents live with an almost constant stream of trucks along the Barton Highway which cuts directly through the town.
00:10Locals have significant safety concerns about the road after a history of serious accidents and fatalities.
00:17We always worry that it will be someone we know.
00:21Unfortunately for many locals that have lived here, it has often been someone we know.
00:27So it can be really scary when you've got your family travelling in and out every day.
00:32Since the beginning of last year, there have been five fatal crashes on the highway.
00:37Data from the New South Wales government shows a history of serious accidents.
00:42From 2014 to 2023, there were a total of 141 crashes.
00:48In that period, five people were seriously injured and another nine people died.
00:55The state government has been working to duplicate the highway, but residents say the community can't afford to wait.
01:02Most of Murram Bateman and a lot of YAS do commute into Canberra, not just for work but for healthcare, for schooling.
01:10And unfortunately, when you're travelling with this many trucks on the road every day, it's really, really nerve-wracking.
01:17The project's first stage was completed in February last year, duplicating seven kilometres of the highway from just north of the ACT border to just south of Kevenies Road.
01:29The second stage, now in its planning phase, will duplicate another 14 kilometres of the highway up to Goode Creek Road.
01:38Another three stages will see the highway eventually duplicated past Murram Bateman to just south of the Yass River, where the road is already a dual carriageway.
01:50Stages one and two are funded with $65 million from the state government and $178 million from the federal government.
01:59Earlier this year, the federal government contributed another $25 million for planning further stages, but there's been no funding commitment for construction of stages three onwards.
02:11In the meantime, almost 14 kilometres of road safety barriers are being installed along the highway and raised line marking will be installed on roads north of Murram Bateman next year.
02:23Despite the government's promises, locals say the highway will only be safe once the duplication is finished.
02:31A long wait for those who drive it every day.