00:00Thank God, we have done the maintenance work related to the issue of gas supply, electric supply, and also the telecommunication.
00:18I have discussed with the telecommunication team to ensure that everything will be repaired as soon as possible.
00:30I have received information that by Friday, the electricity supply to the entire village will be completed.
00:40There are still a few houses that have not been completed.
00:42However, the issue of the owner of the house wanting to return is the second question.
00:46But for the supply, at least it will reach the meter and the fuse will be removed so that the owner of the house is ready to enter.
00:55But the place where the house is not safe, it will not be connected, which has damaged the metering and the DB board.
01:04It is not connected, but which is better, it is installed and the main fuse is removed.
01:09I think the owner of the house is ready to do a load test to ensure that the wiring is good.
01:14Telecom also said that by Friday, the unified services will all be restored for communication.
01:22For petroleum and gas, we have held several meetings.
01:26Inshallah, as everyone knows, the investigation is underway.
01:30It will take a little time.
01:32We want to thoroughly investigate the source and so on.
01:36It will be announced later, if Allah wills it.
01:38When the conclusive evidence is obtained, what issues are related.
01:43We have nothing to hide.
01:45This is all for safety.
01:48Indeed, it will take time.
01:50From the beginning, we have had previous experiences, incidents that are not like this, but almost.
01:56It takes time.
01:58This is because there are various issues that we need to consider before we can reveal or tell what the source is.
02:09It involves many parties.
02:11It involves various expertise.
02:13Geotech, issue integrity of the gas pipeline, etc.
02:18Everything needs to be investigated.
02:20But for now, it is a secure site for further investigation.
02:24As for the source, it will take time.
02:27We have to be patient and wait for the decision or investigation to be made, if Allah wills it.
02:35There will be none.
02:37We are not hiding anything.
02:39But in the beginning, everything was in order.
02:44There were no issues on social media.
02:47Everything was done well according to the SOP.
02:50The implementation of the work in the ROW gas pipeline was done according to the procedure.
02:58There were no issues, no illegal processes, etc.
03:03There were no issues.
03:04We just want to look at the source.
03:06We are looking at the source of the incident.
03:11The most important thing that I have discussed in the ROW is the steps to be taken for the gas pipeline.
03:19We have discussed this with Gas Malaysia.
03:24We will take additional steps to ensure that incidents like this will not happen again.
03:32As for the gas supply, there will be some issues.
03:37We have tried to find a solution.
03:39A large part of the gas supply is for power stations.
03:46There are four power stations involved.
03:50In Serdang, Konop Bridge, Pulau Indah and Kapah.
03:55Two of these can be replaced.
03:58One uses coal, the other uses distilled oil.
04:04But these two can't be replaced because they are gas only.
04:07Konop Bridge and Pulau Indah are in standby mode.
04:11We will see how it goes.
04:12But so far, the electricity supply has not been affected.
04:15It can be distributed to other power plants to meet the needs of the country's electricity supply.
04:23Because it is on the grid, we have been coordinated by the Ministry of Energy
04:29to ensure that the electricity supply is not affected by the gas supply.
04:38Everything is affected.
04:39Villages, Central Village, Sembilan Baru, etc.
04:43Everything will be finished.
04:44Today, there are less than 50 villages that have not been affected.
04:48But there are people who don't want to come.
04:50They want to do a load test to make sure the wiring is intact.
04:53They do a TNB test up to the meter.
04:55But they have to do a test to make sure the wiring is intact.
04:59Everything on this side has been taken care of.
05:01The Harmony Park has been completed.
05:03Except for the ones that are badly damaged.
05:05There are 51 that can't be repaired.
05:11Of course, they will be installed.
05:12But the others can be installed.
05:14But the owners haven't come yet.
05:18Maybe they will take some time for them.
05:21The TNB will wait to do the load test.
05:25That's what will be taken care of.