00:00The police have investigated by re-digging through the concrete pipe installed by a contractor company.
00:07It was found that this concrete pipe was installed within 2.1 metres from the existing road.
00:17Subsequently, it was found that the digging work was done by this contractor not more than 3 metres along the road with a width of 1.5 metres.
00:28The digging and installation work has been carried out for more than 30 metres and is believed to be continued.
00:36The road that crosses the concrete pipe is the road that was passed.
00:42The police found that the digging by this contractor was not more than 3 metres from the road.
00:52The digging and installation work was carried out by 3 excavators, 1 bulldozer and 1 backhoe.
01:00It is being carried out to open the area and examine the condition of the Petronas pipe which is believed to be within 6 to 7 metres.
01:09The police also found that this gas pipe is within 5.6 metres from the road.
01:17It is being carried out to open the area and examine the condition of the Petronas pipe which is believed to be within 6 to 7 metres.
01:27It is being carried out to open the area and examine the condition of the Petronas pipe which is believed to be within 6 to 7 metres.
01:37The distance is estimated in the past.
01:45So far, I can only say that the distance that has been excavated has disturbed the pipe.
01:52It still needs further investigation.
01:54It means that we have to expose the whole pipe from that place to the ground zero.
02:01So, we cannot comment on that at this moment.
02:08Okay, I have told you about the phase.
02:14We will take another 7 to 10 days to stabilize the ground because we have to install the sheet pile on the left and right.
02:22I want to tell you that the hole in the pipe is 7 metres.
02:29So, we have to stabilize the ground.
02:32We have to install the sheet pile on the left and right.
02:39Only then, the ground can be excavated.
02:42And we have to bring the ground out to 6 metres.
02:48So, with the current rain condition, we have to bring out the water from there.
02:54So, that will take 7 to 10 days.
02:57After that, we can go back inside.
02:59So, we can issue an early report within 2 weeks.
03:03So, that is the plan of the technical agencies involved.