• 1 day ago
Red Oak, Texas approved Compass Data Centers' 886-acre expansion four to one while neighbors in their nineties pleaded against it, protesters stood outside a Cherry Valley, Illinois library while Microsoft met behind closed doors, Washington County, Arkansas passed a one-year moratorium, and a fight over banning data centers on federal land stalled the Senate's 495-page permitting bill. Here's what's happening across U.S. data centers:

🏘️ COMMUNITY — Red Oak Approves Compass's 886-Acre Data Center Expansion 4-1 Over Protests. A joint City Council and Planning & Zoning meeting added parcels off FM 2377 to the campus while a lawsuit over the May rezoning is still pending. Expansion pushes the Oglesby Road campus to ~886 acres; the original 800-acre zoning was approved in May. Opponents rallied at Watkins Park, then waited through a 30-minute executive session to speak. Compass says it has invested $100M+ in Red Oak over six years; supporters wore red shirts.

🏘️ COMMUNITY — Cherry Valley Residents Protest Outside as Microsoft Meets Behind Closed Doors. A couple dozen protesters gathered at the village library near Rockford, Illinois while Microsoft briefed select community members inside. Valley Orchard owner Raoul Bergersen says the data center could sit beside his trees — water, drainage and pollination at risk. Protesters cite bright lights, noise, water pollutants and rising electricity costs. Microsoft and the village did not respond to requests for comment; no acreage or MW figures disclosed.

⚖️ LEGAL — Washington County, Ark. Passes One-Year Data Center Moratorium in Fayetteville. The Quorum Court approved Justice of the Peace Evelyn Rios Stafford's pause on new applications and approvals in unincorporated areas Thursday night. Cleared the County Services Committee 9-5 with one abstention before Thursday's final vote. Amendments exclude broadband/telecom facilities and require a Planning Board public hearing. Follows Siloam Springs' 6-month pause (Nov. 3) and

Category

🤖
Tech
Transcript
00:00A Texas City Council just approved a data center campus the size of a small town.
00:05Four to one.
00:07While neighbors in their 90s begged them not to.
00:10Outside Rockford, Illinois, protesters stood in the cold while Microsoft met behind closed doors.
00:17An Arkansas county hit pause for a full year.
00:21And the fight has now stalled a major bill on the Senate floor.
00:26In Red Oak, Texas, south of Dallas, the fight over Compass Data Center's campus just got bigger.
00:34And the residents lost again.
00:37At a packed joint meeting of the City Council and Planning and Zoning Commission.
00:42Officials voted four to one to add parcels along FM 2377 to the project.
00:49Pushing the campus on Oglesby Road to roughly 886 acres.
00:55Opponents rallied at Watkins Park before the meeting.
00:58Then waited through a 30-minute closed session to speak.
01:02Eugene and Betty Gentry, a couple in their 90s who live near the site, told the council they fear for
01:09their quality of life.
01:11And neighbor Heidi Johanna warned of noise and light.
01:14The original 800-acre rezoning from May is still being challenged in court.
01:19Compass says it has invested more than $100 million in Red Oak over six years and calls itself a 100
01:28-year neighbor.
01:30Several hundred miles north, in Cherry Valley, Illinois, just outside Rockford, the opposition is aimed at one of the biggest
01:39names in tech.
01:40On Wednesday evening, a couple dozen residents stood outside the village library with signs while
01:46Microsoft representatives met inside with a hand-picked group of community members.
01:52Raul Bergersen, who owns Valley Orchard, says the proposed data center could sit right beside his trees, threatening his water,
02:03drainage, pollination, and revenue.
02:06Dalton Jiraki, whose family farms nearby, worries about pollutants reaching the water table.
02:13Deborah Stevens told reporters Microsoft should build at a site known as Block 39 instead.
02:20And Sam Gonzalez pointed to electricity costs.
02:24Janet McComb said what residents want most is transparency from the village.
02:28Neither Microsoft nor Cherry Valley officials responded to requests for comment.
02:35And no acreage, power figure, or price tag has been made public so far.
02:41That kind of pressure is now producing hard votes.
02:45In Fayetteville, Arkansas, the Washington County Quorum Court on Thursday night approved a one-year moratorium on new data.
02:54Center applications and approvals in the county's unincorporated areas.
02:59Justice of the Peace Evelyn Rios Stafford sponsored the measure, which cleared the county services committee 9-5 with one
03:07abstention before the final vote.
03:10Amendments exclude broadband and telecom facilities and require a public hearing before the planning board.
03:18County Attorney Brian Lester said no data center applications have been filed yet,
03:23but pointed to a lawsuit facing Pulaski County over waiting too long.
03:28The backdrop is Server Farms Project in Clarksville, expected to draw up to 1.5 million gallons of water a
03:37day.
03:38Siloam Springs passed a six-month pause on November 3rd, and this week Iowa's Kossuth County supervisors voted 3-2
03:46for a six-month moratorium.
03:49In Washington, the backlash has reached the Senate floor.
03:54A 495-page permitting bill, the Bipartisan American Affordability and Jobs Act,
04:01stalled Thursday after Senator Ron Wyden of Oregon pushed an amendment to ban data centers on federal land.
04:09Supporters say the bill would force a $35 billion infusion into the grid.
04:15Grid Strategies estimates data centers would pay $55 billion in transmission costs.
04:22Over 10 years, $35 billion more than today.
04:26Senator Sheldon Whitehouse of Rhode Island said the day of data center freeloading ends when the bill passes.
04:34Senator Edward Markey of Massachusetts countered that it puts developers on a greased-up slide.
04:41Democrats had only six votes to spare to reach 60, and opponents now want to push the whole bill into
04:47January.
04:48A Harvard study in the mix finds hyperscale data centers emit 25.7 million metric tons of carbon dioxide a
04:58year.
04:59And the reason the money fight matters comes down to who pays for the wires.
05:05Utilities across the country have asked the Federal Energy Regulatory Commission to require data centers to sign long-term transmission
05:14contracts before upgrades are built.
05:16In PJM, the utilities want large loads to pay for at least 80% of the transmission service they request
05:25for a minimum of 10 years.
05:27Backed by collateral that starts at 25% of what is owed and rises to the full amount by the
05:34time service begins.
05:36California and New York utilities propose 15-year terms.
05:40And MISO floats a three-way contract between the grid operator.
05:44Water, utility, and data center running up to 20 years.
05:49The filings answer a June show cause order FERC sent to the six grid operators it oversees.
05:56Five have responded, with the Southwest Power Pool due this week.
06:01Comments are due December 7th.
06:04The grid is only half the story.
06:07Water tells the other half.
06:09And in North Carolina's Research Triangle the numbers are stark.
06:13Durham has about 75 days of easily accessible water left if no rainfalls.
06:19And 145 days of total supply.
06:23With Falls Lake at its lowest level since 2007.
06:27Durham identified six customers that could be data centers.
06:31The four it can isolate use about 1.88 million gallons a month.
06:36Roughly 0.2% of city demand.
06:40In Raleigh, nearly two-thirds of water goes to homes.
06:44Industry is 4%.
06:45And summer lawn irrigation alone can reach 17-18 million gallons a day.
06:52Raleigh Waters Ed Buchan says there are no large generative AI data centers in its territory yet.
06:58Both cities have paused new ones anyway.
07:02Six months in Raleigh.
07:03Nine in Durham.
07:05State lawmakers are taking notice.
07:08And nowhere louder than Texas.
07:11Governor-elect Gina Hinojosa went on Fox News Thursday to call for a statewide moratorium on new.
07:18Data center permits until the legislature passes protective laws.
07:23Saying that Texas does not have laws to protect Texans.
07:27The same day, Republican State Senator Charles Perry of Lubbock filed Senate Bill 338 with 16 co-authors.
07:37All but one Republican.
07:39The bill would apply to data centers built after September 1st of next year.
07:44Limit them to four approved cooling methods.
07:47And require annual water use reporting.
07:50The Public Utility Commission could set limits on water, light, noise, and setbacks.
07:58And facilities that fail to comply could be barred from connecting to the grid.
08:03Cities, counties, and school districts could not grant more than a 50% property tax break.
08:10Riley Rodriguez of Don't Drain Texas called the bill shallow.
08:14The session opens January 12th.
08:18And the financial side of this boom is not all deep pockets.
08:23Hyperscale Data.
08:25A former Bitcoin miner that sold the last of its coins.
08:28Told investors in a filing Wednesday that it needs another $74.8 million.
08:35Between now and March to finish an AI data center in Dowajac, Michigan.
08:41The project costs $122.1 million.
08:46With $47.3 million paid through October.
08:50Since late July the company has sold roughly $1,113 Bitcoin for about $74 million.
08:58Unrestricted cash stood at $17 million at the end of September against $231 million in current liabilities.
09:07And the filing cites substantial doubt about its ability to continue.
09:12The prize is a 20-megawatt contract with an unnamed California AI provider.
09:18Potentially worth $1.2 billion if two five-year extensions kick in.
09:32It helps us cover more of these stories.

Recommended