00:00A Texas City Council just approved a data center campus the size of a small town.
00:05Four to one.
00:07While neighbors in their 90s begged them not to.
00:10Outside Rockford, Illinois, protesters stood in the cold while Microsoft met behind closed doors.
00:17An Arkansas county hit pause for a full year.
00:21And the fight has now stalled a major bill on the Senate floor.
00:26In Red Oak, Texas, south of Dallas, the fight over Compass Data Center's campus just got bigger.
00:34And the residents lost again.
00:37At a packed joint meeting of the City Council and Planning and Zoning Commission.
00:42Officials voted four to one to add parcels along FM 2377 to the project.
00:49Pushing the campus on Oglesby Road to roughly 886 acres.
00:55Opponents rallied at Watkins Park before the meeting.
00:58Then waited through a 30-minute closed session to speak.
01:02Eugene and Betty Gentry, a couple in their 90s who live near the site, told the council they fear for
01:09their quality of life.
01:11And neighbor Heidi Johanna warned of noise and light.
01:14The original 800-acre rezoning from May is still being challenged in court.
01:19Compass says it has invested more than $100 million in Red Oak over six years and calls itself a 100
01:28-year neighbor.
01:30Several hundred miles north, in Cherry Valley, Illinois, just outside Rockford, the opposition is aimed at one of the biggest
01:39names in tech.
01:40On Wednesday evening, a couple dozen residents stood outside the village library with signs while
01:46Microsoft representatives met inside with a hand-picked group of community members.
01:52Raul Bergersen, who owns Valley Orchard, says the proposed data center could sit right beside his trees, threatening his water,
02:03drainage, pollination, and revenue.
02:06Dalton Jiraki, whose family farms nearby, worries about pollutants reaching the water table.
02:13Deborah Stevens told reporters Microsoft should build at a site known as Block 39 instead.
02:20And Sam Gonzalez pointed to electricity costs.
02:24Janet McComb said what residents want most is transparency from the village.
02:28Neither Microsoft nor Cherry Valley officials responded to requests for comment.
02:35And no acreage, power figure, or price tag has been made public so far.
02:41That kind of pressure is now producing hard votes.
02:45In Fayetteville, Arkansas, the Washington County Quorum Court on Thursday night approved a one-year moratorium on new data.
02:54Center applications and approvals in the county's unincorporated areas.
02:59Justice of the Peace Evelyn Rios Stafford sponsored the measure, which cleared the county services committee 9-5 with one
03:07abstention before the final vote.
03:10Amendments exclude broadband and telecom facilities and require a public hearing before the planning board.
03:18County Attorney Brian Lester said no data center applications have been filed yet,
03:23but pointed to a lawsuit facing Pulaski County over waiting too long.
03:28The backdrop is Server Farms Project in Clarksville, expected to draw up to 1.5 million gallons of water a
03:37day.
03:38Siloam Springs passed a six-month pause on November 3rd, and this week Iowa's Kossuth County supervisors voted 3-2
03:46for a six-month moratorium.
03:49In Washington, the backlash has reached the Senate floor.
03:54A 495-page permitting bill, the Bipartisan American Affordability and Jobs Act,
04:01stalled Thursday after Senator Ron Wyden of Oregon pushed an amendment to ban data centers on federal land.
04:09Supporters say the bill would force a $35 billion infusion into the grid.
04:15Grid Strategies estimates data centers would pay $55 billion in transmission costs.
04:22Over 10 years, $35 billion more than today.
04:26Senator Sheldon Whitehouse of Rhode Island said the day of data center freeloading ends when the bill passes.
04:34Senator Edward Markey of Massachusetts countered that it puts developers on a greased-up slide.
04:41Democrats had only six votes to spare to reach 60, and opponents now want to push the whole bill into
04:47January.
04:48A Harvard study in the mix finds hyperscale data centers emit 25.7 million metric tons of carbon dioxide a
04:58year.
04:59And the reason the money fight matters comes down to who pays for the wires.
05:05Utilities across the country have asked the Federal Energy Regulatory Commission to require data centers to sign long-term transmission
05:14contracts before upgrades are built.
05:16In PJM, the utilities want large loads to pay for at least 80% of the transmission service they request
05:25for a minimum of 10 years.
05:27Backed by collateral that starts at 25% of what is owed and rises to the full amount by the
05:34time service begins.
05:36California and New York utilities propose 15-year terms.
05:40And MISO floats a three-way contract between the grid operator.
05:44Water, utility, and data center running up to 20 years.
05:49The filings answer a June show cause order FERC sent to the six grid operators it oversees.
05:56Five have responded, with the Southwest Power Pool due this week.
06:01Comments are due December 7th.
06:04The grid is only half the story.
06:07Water tells the other half.
06:09And in North Carolina's Research Triangle the numbers are stark.
06:13Durham has about 75 days of easily accessible water left if no rainfalls.
06:19And 145 days of total supply.
06:23With Falls Lake at its lowest level since 2007.
06:27Durham identified six customers that could be data centers.
06:31The four it can isolate use about 1.88 million gallons a month.
06:36Roughly 0.2% of city demand.
06:40In Raleigh, nearly two-thirds of water goes to homes.
06:44Industry is 4%.
06:45And summer lawn irrigation alone can reach 17-18 million gallons a day.
06:52Raleigh Waters Ed Buchan says there are no large generative AI data centers in its territory yet.
06:58Both cities have paused new ones anyway.
07:02Six months in Raleigh.
07:03Nine in Durham.
07:05State lawmakers are taking notice.
07:08And nowhere louder than Texas.
07:11Governor-elect Gina Hinojosa went on Fox News Thursday to call for a statewide moratorium on new.
07:18Data center permits until the legislature passes protective laws.
07:23Saying that Texas does not have laws to protect Texans.
07:27The same day, Republican State Senator Charles Perry of Lubbock filed Senate Bill 338 with 16 co-authors.
07:37All but one Republican.
07:39The bill would apply to data centers built after September 1st of next year.
07:44Limit them to four approved cooling methods.
07:47And require annual water use reporting.
07:50The Public Utility Commission could set limits on water, light, noise, and setbacks.
07:58And facilities that fail to comply could be barred from connecting to the grid.
08:03Cities, counties, and school districts could not grant more than a 50% property tax break.
08:10Riley Rodriguez of Don't Drain Texas called the bill shallow.
08:14The session opens January 12th.
08:18And the financial side of this boom is not all deep pockets.
08:23Hyperscale Data.
08:25A former Bitcoin miner that sold the last of its coins.
08:28Told investors in a filing Wednesday that it needs another $74.8 million.
08:35Between now and March to finish an AI data center in Dowajac, Michigan.
08:41The project costs $122.1 million.
08:46With $47.3 million paid through October.
08:50Since late July the company has sold roughly $1,113 Bitcoin for about $74 million.
08:58Unrestricted cash stood at $17 million at the end of September against $231 million in current liabilities.
09:07And the filing cites substantial doubt about its ability to continue.
09:12The prize is a 20-megawatt contract with an unnamed California AI provider.
09:18Potentially worth $1.2 billion if two five-year extensions kick in.