Black Hills Corporation is set to build and own the new generation serving Google’s planned Wyoming data center while also managing the microgrid. Google is the contracted data center customer through 2048, giving investors a long-term framework for assessing the project’s significance to BKH.

For informational and educational purposes only. Not financial advice.

#BKH #Google #DataCenters #EnergyInfrastructure

Category

🗞
News
Transcript
00:00An AI data center needs chips.
00:03It also needs electricity.
00:05Google has contracted a utility to supply it,
00:08and that utility is putting $1.8 billion of its own capital into new generation.
00:15Black Hills expects that project to contribute
00:18about $150 million of annual net income by 2030.
00:24That is roughly half of the $299.8 million the whole company reported in 2025,
00:32an illustrative comparison to a year already closed.
00:37Black Hills is a relatively overlooked, publicly traded American utility,
00:42and this is one of the larger things it has ever agreed to build.
00:47The market noticed.
00:48The filing was accepted at 4, 19 in the afternoon on October 6,
00:54after the close, so after-hours trading could already react that evening.
00:59October 7 was the first full regular session after the announcement.
01:05Black Hills opened at 74.79 and finished that session up 7.21%.
01:11We are not claiming the filing caused the move, only that this is the sequence.
01:17At 76.25 million shares outstanding,
01:22that one session implies roughly $389 million of equity market value repricing.
01:28That is our calculation, not a company disclosure,
01:33and it does not say the project created $389 million of value.
01:38Resist the arithmetic.
01:41You cannot divide $389 million by $150 million and call the stock cheap.
01:47The project is not built,
01:49and one day of trading does not tell you what a contract to $2,048 is worth.
01:55For that you need to know who invests, who owns, and who collects.
01:59What was actually signed?
02:02Black Hills furnished this to the SEC on October 6.
02:06Furnished, not filed,
02:08everything forward-looking inside it is a company expectation,
02:12not an audited result.
02:14It names two agreements,
02:16one for the service,
02:17one for the generation itself,
02:19both running through 2048.
02:22Now the physical shape of it.
02:24This is Black Hills' own diagram of the project.
02:29Two separate paths feed one data center.
02:32On the first path,
02:34Black Hills will provide up to 590 megawatts
02:37of grid-connected energy service.
02:40That 590 is 564 megawatts of new natural gas generation
02:46it will build and own through a non-regulated affiliate,
02:50plus 26 megawatts from market purchases and retail service
02:55under an industrial tariff.
02:57Note that phrase,
02:59non-regulated affiliate.
03:01The plant is owned outside the regulated utility.
03:05On the second path sit approximately 2.1 gigawatts
03:09of Wyoming-based third-party resources.
03:12Black Hills does not own those.
03:14It manages their output through a private microgrid.
03:17The company describes a total resource mix
03:21of 2.7 gigawatts,
03:23including reserve margins.
03:25Note what none of those is.
03:27The document never states the data
03:29center's own electrical load.
03:32Now the money.
03:33Black Hills plans to invest $1.8 billion
03:37between 2027 and 2029
03:41to build that 564 megawatts.
03:44That is the company's own generation investment,
03:48not the value of the Google contract,
03:50and it excludes transmission.
03:53Google has provided $399 million of advances
03:57for long lead-time equipment,
04:00refundable,
04:00and Black Hills expects to reimburse them
04:03by June 30, 2027.
04:06So that is not money the utility keeps.
04:09The project is expected to provide
04:12approximately $150 million
04:14of net income in 2030.
04:18And across the full term,
04:20Black Hills expects approximately
04:22$2.4 billion of unlevered free cash flow
04:26through 2048.
04:28A figure the document says
04:30is already net of the $1.8 billion
04:33of capital expenditures.
04:35Refundable and reimbursed.
04:37That is what the sentence says.
04:40So how does a utility earn
04:42on power it does not own?
04:44The document describes two engines.
04:47First, a contracted return
04:49on the generation Black Hills does own,
04:52beginning when construction begins in 2027
04:55on an asset fully depreciated by 2048.
04:59Second, microgrid management fees
05:03for coordinating dispatch and reliability
05:05across the contracted portfolio,
05:08beginning late 2027
05:10and rising on a contractually defined ramp.
05:14What the document never gives is a rate.
05:17It says risk-adjusted return
05:19and it stops there.
05:21Those are the mechanics.
05:23Here is the clock.
05:25Service is planned to begin in late 2027,
05:29the $1.8 billion is spent
05:32across 2027 to 2029.
05:36The project is expected
05:37to reach peak load in 2030
05:39and the agreements run to 2048.
05:43How big is this for this company?
05:46Here is the company it belongs to.
05:49In fiscal 2025,
05:52Black Hills reported $299.8 million
05:55of net income.
05:57So a project expected to contribute
06:00approximately $150 million in 2030
06:03is about half of fiscal 2025
06:07consolidated net income.
06:09It spans different years,
06:11so it is scale, not a forecast.
06:14And consolidated is the right word.
06:17Net income available to common shareholders
06:19was a different line,
06:21$291.6 million.
06:24On capital,
06:25the 10K's own line
06:27is total capital expenditures.
06:30$889.8 million
06:32in fiscal 2025,
06:35a figure its own footnote says
06:37includes accruals,
06:38not only cash paid.
06:40The $1.8 billion
06:42is about 2.0 times that,
06:45a three-year program
06:46set against a single year.
06:47One caveat,
06:50Black Hills is itself
06:51mid-merger with Northwestern.
06:53So that comparison
06:55is a historical yardstick,
06:57not the combined company's base.
06:59And the part a press release
07:01leads with last.
07:03The agreements provide
07:04for full recovery
07:05of all-generation capital investment
07:08over the contract term.
07:10The release is specific
07:11about protections,
07:13so let's be specific back.
07:14It describes cost pass-through,
07:17stranded asset recovery,
07:19early termination,
07:21and collateral
07:21behind the data center's commitments.
07:24And the chief executive's
07:25quote goes further
07:26that Google bears
07:28all costs of serving it.
07:30What stays with Black Hills
07:32is named in its own
07:33forward-looking statement,
07:35approvals,
07:36counterparties,
07:36and construction.
07:38A release that describes protections
07:40is not a project without risk.
07:43The approvals say the same thing
07:45in dates.
07:46Two granted in 2026,
07:49the Robinson substation certificate,
07:52and the air quality permit.
07:54Three filed and waiting.
07:56And one,
07:57the company says it intends
07:59to file in the fourth quarter,
08:00which as of this release
08:02has not been filed at all.
08:04So here is what this release
08:06does not settle.
08:07One,
08:08how fuel and commodity price exposure
08:10is allocated.
08:12It describes cost pass-through protections
08:14in general terms,
08:16but does not separately detail
08:18the fuel cost formulas,
08:19which is not the same
08:21as leaving them unprotected.
08:23Two,
08:24what the 2.1 gigawatts
08:25of third-party resources
08:27actually are.
08:28Three,
08:29what return Black Hills
08:31earns on the $1.8 billion.
08:33It says risk-adjusted
08:35and gives no number.
08:37And four,
08:38how that $1.8 billion
08:39actually gets financed.
08:42Black Hills is not selling AI chips,
08:44and it is not running
08:45Google's data center.
08:47Its opportunity is supplying
08:49and managing the electricity
08:51those systems need.
08:53Whether that becomes shareholder value
08:55turns on three things
08:57you can actually check.
08:58Can it finance the $1.8 billion?
09:01Can it build and permit on schedule?
09:04And does the contribution
09:05approach $150 million by 2030?
09:09The real question
09:10is not whether AI needs more power.
09:13It is how much of that demand
09:15Black Hills
09:16can turn into lasting shareholder value.
09:19Where the filings were specific,
09:21we quoted them.
09:22Where they were not,
09:24that we said so.
09:25I don't know.