A council in Tasmania’s north-west says AI company Firmus appears to have carried out illegal work at the site of one of their proposed data centres. While the company says it didn't need approval for the activities being carried out, it has stopped work while the council investigates further.

Category

📺
TV
Transcript
00:02This is the site of a proposed 52 megawatt data centre in northwest Tasmania.
00:08Today it's all quiet, but yesterday it was a different story.
00:13Members of the public have provided photographic evidence
00:16which suggests quite significant excavations have taken place
00:19and material has been taken to site along with site offices and the like.
00:25The Latrobe Council says the activity could be illegal.
00:28Firmus Technologies has an approved forest practices plan for the site
00:32to fell trees and remove weeds and stumps.
00:36But the local mayor says it appears the company has gone well beyond the plan's scope.
00:40It's certainly feeding into a proverbial forest form of concern in our community.
00:47After visiting the site yesterday, the council let Firmus know
00:50of its intention to issue an enforcement notice.
00:52The company agreed to stop works.
00:55Further investigations will take place next week.
00:58A Thermus spokesperson said the works underway with general site maintenance
01:02did not require planning approval and are separate to the proposed business application.
01:08They said no major works would get underway until the appropriate approvals had been received.
01:14Some local residents already unhappy about the idea of the data centre in their community
01:18are anxious about the latest development.
01:21We're upset at the idea of the water that's going to be used, the energy that's going to be used,
01:28all the other things.
01:29But the arrogance that they showed towards the local population.
01:35The Greens have praised the Latrobe Council for intervening.
01:39It's very welcome to see any level of government standing up to big AI data centres at the moment
01:45because we're sure not getting that from the state government.
01:48The state government is currently considering a request by the Latrobe Council
01:52to assess the data centre proposal as a major project.
01:56The End