00:00who would have thought building a cliff road requires this much precision first step wooden
00:04stakes marked into the rock face set the boundary get this wrong and everything after is wasted
00:09then wooden formwork is assembled rebar mesh laid concrete poured creating a retaining wall
00:15locked directly into the mountain blocking falling rocks above and flash floods below
00:19once cured soil fills every gap in collapse section leveling the foundation large crushed
00:25stone is spread and compacted repeatedly by road roller building a load-bearing skeleton skip this
00:31and it sinks later holes are drilled into the road surface rebar inserted mesh laid connecting road
00:37and retaining wall into one unified structure finally hot asphalt is laid and compacted until
00:42dense and level lane markings painted this cliff lifeline officially opens now the second stretch
00:48originally a muddy path that sank with every step first the slope soil is fully excavated and leveled
00:54then steel wire mesh cages packed with stones build gabion walls stabilizing the entire slope
01:00fine sand fills every gap and solidifies the road base guard rail posts are installed along the cliff
01:06edge only then does asphalt paving begin a crumbling dangerous cliff road transformed into a surface
01:12place people can finally trust
01:13you