00:00I'm Alistair Dalton, the Scotsman's transport correspondent.
00:03I'm in the centre of Edinburgh today to go inside one of the city's most famous crossings,
00:10North Bridge, which spans Waverley Station,
00:14which is undergoing an £86 million refurbishment.
00:19The bridge has been under wraps for the last eight years,
00:23and next year the work should be finally complete.
00:27We were taken behind the scenes to see at close quarters the most significant work on the bridge since the 1930s,
00:34including restoration of stonework and some intricate painting.
00:39My name's Rory McFadden. I'm the project director for Balfour Beedie on the Edinburgh North Bridge refurbishment project.
00:45The main work we've been involved in was building the temporary work scaffold, first of all.
00:48That allowed us access to undertake the refurbishment of the structural steelwork,
00:52the concrete bridge deck, the blasting and painting of the steelwork then,
00:56and also the reinstallation of the facade.
00:58The bridge was in much worse condition than anyone could expect to find it.
01:01It wasn't until we built our access scaffold,
01:04it was the first time anyone had up-close access to the bridge since the 1990s.
01:08A lot of the structural steelwork, or all of the structural steelwork,
01:11was covered in a thick, bituminous paint,
01:14and it wasn't until we started removing that
01:16that we could understand the true condition of the steelwork that was obscured behind that paint.
01:20It's a William Arle structure, also famous for the Forth Bridge,
01:24and other bridges throughout the UK, and Gooden Tower Bridge down in London.
01:27There was a famous quote, or one of the famous quotes by Sir William Arle was that
01:31scaffolding of a peculiar nature had to be constructed when he built the bridge,
01:35and over a hundred years later we're still constructing scaffold of a peculiar nature
01:40to undertake the refurbishment.
01:42We've been working on the project since 2018, but we are near in completion now.
01:45Over the last number of months we started applying the final gold paint to the structure,
01:50and that's given everybody a bit of morale boost to get it over the line,
01:54so the work should be substantially complete by Spring 2026.
01:58We'll slowly unveil the bridge, removing the scaffolds,
02:01and we should be off the structure by Summer 2026.
02:04My name's Councillor Stephen Jenkinson,
02:06and I'm the Transport and Environment Convener for the City of Edinburgh Council.
02:10So this is a hugely important piece of Edinburgh's transport infrastructure.
02:16It's a main transport link to move people north and south,
02:21and it's a very historic piece of Edinburgh's architecture.
02:26Why the need for all this refurbishment work?
02:28There were structural defects identified which we needed to put right
02:33to ensure that this bridge is protected for future generations.
02:36There are a number of reasons for it.
02:42It's a hugely complex project.
02:45It's been over 90 years since the last major refurbishment of this bridge,
02:51and through that time there has been obviously some wear and tear
02:56that we're looking to rectify.
02:57We have to take into account that the bridge is above a major train station,
03:02which makes the project quite complex,
03:06and also we've been very careful to ensure that we've maintained access to the bridge,
03:12north and south, and south and north,
03:14both for pedestrians and for traffic at various points of the project,
03:19which has essentially elongated the process.
03:21We have also elongated the process.
03:252
03:264
03:274
03:285
03:295
03:306
03:317
03:327
03:348
03:358
03:369
03:378
03:3810
03:399
03:409
03:418
Comments