00:00NLEX has already started the installation of a horizontal metal gear deck after the Marilao Bridge was damaged on March 19
00:07because a truck with an overheight of 4.27 meters was attached to the so-called bridge.
00:13The vehicle can pass through NLEX, but the truck has a height of 4.9 meters.
00:18According to the leadership of NLEX, they will strive to fix the bridge until Friday, March 28.
00:24This is also in line with the directive of DOTR Secretary Vince Dizon
00:29that the bridge should be built within a week.
00:33Yesterday afternoon, toll fees were free in the northbound portion from the so-called Toll Plaza to Maycawayan Exit.
00:41We hope that the traffic will increase again because we experienced on Friday night until Saturday night, around 9 p.m.,
00:56It will continue until this morning. We are in light traffic.
01:00But because we will close additional lanes, so that when the metal beam is replaced, the traffic will be less congested,