00:00In 2025, a total of 12 billion ringgit will be allocated for the acquisition of assets and ATMs.
00:13Among the main acquisition assets that have been approved this year include
00:19105mm PAK Hot Wiser for land forces, surface-to-surface missiles for use,
00:293 medium-altitude units, long-endurance unmanned aerial systems,
00:39and many others that need not be mentioned.
00:45In addition, we will continue to ensure the development and progress of important asset construction
00:53to achieve the progress scheduled.
00:56This includes the LCS-1, which is expected to achieve 96.52%.
01:08The LCS-1 has now begun the acquisition test of ports and sea.
01:17The LCS-2, LCS-3, LCS-4, and LCS-5 are expected to achieve 86.61%,
01:2976.60%, 65.05%, and 48.72%.
01:40The LCS-2 has also been lowered into the water and is currently undergoing a setting to work.
01:49Meanwhile, the LCS-3 is in the final stages of preparation to be lowered into the water,
01:57which is scheduled for January 2026.
02:02For the construction of the second batch of LMS ships,
02:06the progress of the work for the third batch of ships is expected to reach 13.8% overall in June 2025.
02:22The LMS B-2-1, B-2-2, and B-2-3 are expected to achieve 17.1%, 13.9%, and 10.4%.
02:45At the same time, for the Kai FA-50, Block 20 is achieving a status of progress up to 48% for the time being.
02:58We will monitor this development carefully this year,
03:04and according to the plan, the first two ships will be received in October 2026.
03:13In addition, we are working on the acquisition of the maritime patrol aircraft for the purpose of monitoring the maritime area,
03:25and this asset is expected to be received in June and September 2026.
03:33In addition to continuing and carrying out various important processes to complete and modernize our defense infrastructure,
03:43the Ministry will continue to pay attention to the efforts to meet the needs of assets and efforts to face non-traditional threats.