Temporary electricity supply must be provided to blackout-hit areas on Sabah's east coast, with priority given to critical public infrastructure, schools, and examination centres, says Prime Minister Datuk Seri Anwar Ibrahim.

He also urged Sabah Electricity (SE) to expedite restoration works so that full power can be restored ahead of schedule.

Read more at https://tinyurl.com/2szbx8m6

WATCH MORE: https://thestartv.com/c/news
SUBSCRIBE: https://cutt.ly/TheStar
LIKE: https://fb.com/TheStarOnline
Transcript
00:01Prime Minister Datuk Sri Anwar Ibrahim has urged Sabah Electricity to expedite restoration works following a major power outage affecting
00:10Sabah's east coast.
00:12He said temporary electricity supply must be provided to affected areas, with priority given to critical public infrastructure, schools and
00:21SPM examination centres.
00:23In a social media post on Saturday, Anwar stressed that every hour mattered to residents affected by the disruption, particularly
00:32students preparing for their Sijil Pelajaran Malaysia examinations.
00:36The blackout began on Thursday after a 275kV transmission tower collapsed in Ranau, cutting off two main circuits connecting Sabah's
00:46west and east coasts.
00:47The incident affected more than 153,000 registered consumers across eight districts.
00:54Meanwhile, Sabah Electricity is implementing a three-hour rotational load-shedding system while restoration works continue, with full power supply
01:03expected to be restored by Dec. 3 at the latest.