Natapos na ang pagkukumpuni sa EDSA-Magallanes flyover sa Makati at halos patapos na rin ang Phase 1 ng rehabilitasyon ng EDSA, ayon sa Department of Public Works and Highways.


24 Oras is GMA Network’s flagship newscast, anchored by Mel Tiangco, Vicky Morales and Emil Sumangil. It airs on GMA-7 Mondays to Fridays at 6:30 PM (PHL Time) and on weekends at 5:30 PM. For more videos from 24 Oras, visit http://www.gmanews.tv/24oras.

#GMANews #SerbisyongTotoo #BreakingNews
Watch the latest news stories from GMA Network's trusted news programs on the GMA Play app.
Download now on Google Play and App Store.
Also available on GMANetwork.com/GMAPlay and Android TVs!
GMA Network promotes healthy debate and conversation online. Any abusive language that does not facilitate productive discourse will be blocked from this post.
For more updates, visit this link: https://www.youtube.com/playlist?list=PLCpdvYcv59AjcPwb7dvUt3oCLasY96Dta
For live updates and highlights, click here: https://www.youtube.com/playlist?list=PLCpdvYcv59AiKdYH_GDSU7sBgfc7Cd1de
Breaking news and stories from the Philippines and abroad:
GMA News Portal: http://www.gmanews.tv
YouTube: https://www.youtube.com/@gmanews2026
Facebook: http://www.facebook.com/gmanews
TikTok: https://www.tiktok.com/@gmanews
Twitter: http://www.twitter.com/gmanews
Instagram: http://www.instagram.com/gmanews
GMA Network Kapuso programs on GMA Pinoy TV: https://gmapinoytv.com/subscribe

Category

🗞
News
Transcript
00:00We finished the EDSA Magallanes Flyover at almost finished the phase 1 of rehabilitation of EDSA
00:09according to the Department of Public Works and Highway.
00:12And we finished the E.J. Gomez.
00:18We finished the southbound lane of Magallanes Flyover at Makati City.
00:23Pansamantalang isinara sa mga motorista ang Magallanes Flyover bilang bahagi ng malawakang rehabilitasyon ng EDSA.
00:31Nagsimula ang repair works noong April 1 hanggang kahapon, April 5.
00:36Inayos ang asfalto, expansion joints at retrofitting ng flyover.
00:41Nagdulot din ng mabigat na daloy ng trapiko ang pansamantalang pagsasara ng naturang flyover
00:46na sinabayan pa ng pagtigil ng operasyon ng MRT nitong huliwi.
00:51Ayon kay DPWH Secretary Vince Dizon, aabot sa P180 million pesos ang pondong ginamit ng gobyerno sa repair works dito.
01:01Sinara namin muna itong EDSA Magallanes kasi medyo safety issue to eh.
01:06So inayos lang natin yung mga joints noong flyover para masigurado na walang abirya.
01:15So minadagi natin tapos yung mga konting mga aayusin na gang, aayusin na gang during the week pero hindi na
01:22ito isasara.
01:23Ano na lang, magtatrabaho na lang dito yung usual work time natin ng 10pm to 4am.
01:28Kasabay ng Magallanes Flyover Repair Works, ang 24-7 na pagkumpuni ng Phase 1 ng EDSA Rehabilitation mula sa EDSA
01:37Taft hanggang Orense sa Makati.
01:39Inayos ang ilang bahagi ng kalsada na may baku-baku o nasirang aspalto sa Taft at Rojas Boulevard sa Pasay
01:46City.
01:47Ayon kay Dizon, halos 2 months ahead of schedule ang natapos na Phase 1 EDSA Rehabilitation.
01:53Mararamdaman ng mga kababayan natin yung talagang kaibahan ng pagbabiyahe sa EDSA.
02:00Kumpira sa pagbabiyahe dati na talagang medyo napakasama talaga.
02:06Sira-sira, bako-bako. So ngayon talagang smooth na.
02:13So ang challenge ngayon, Phase 2.
02:15Ayon sa DPWH, magsisimula ang bidding ng Phase 2 EDSA Rehabilitation mula Orense hanggang Monumento ngayong buwan at ang aktwal
02:25na operasyon ay sisimulan sa Mayo.
02:28EJ Gomez, Nakatutok 24 Oras.
02:32EJ Gomez, Nakatutok 24 Oras.