52 ಕೋಟಿ ವೆಚ್ಚದಲ್ಲಿ 33 ಕ್ರೆಸ್ಟ್‌ಗೇಟ್‌ಗಳನ್ನು ತೆರವುಗೊಳಿಸಿ, ತುಂಗಭದ್ರಾ ಜಲಾಶಯಕ್ಕೆ ಹೊಸ ಕ್ರಸ್ಟ್​​​ಗೇಟ್​​ ಅಳವಡಿಸುವ ಯೋಜನೆಗೆ ಇಂದು ಪೂಜೆ ನೆರವೇರಿಸುವ ಮೂಲಕ ಕೆಲಸ ಆರಂಭಿಸಲಾಗಿದೆ.

Category

🗞
News
Transcript
00:00Today we conducted puja actually and then in that we also started
00:30the work by cutting one gate also, gate number 18 and then even this contractor is ready
00:37to complete the work at the LAS that means within four to five months but first gate
00:42we will try to install this month itself so that actually if any problem is there it can
00:46be rectified. For first gate we will take some good time actually.
00:52We are going to start actually 20th of this month that is first removal of the gate it will take
00:57actually two to three days actually for removal of the gate and then one gate one gate and then
01:03that gate number 18 will complete actually this month itself again remaining 32 gates even they
01:09are ready to complete actually eight gates in a month because they want to engage actually three
01:17agencies that means one this one agency out of three units that means groups each group actually
01:25will complete uh three places we will keep i think uh we are thinking actually nine to eight to nine
01:32actually they complete in a month in that way we will go also for within four months we will easily
01:37complete all the gates so we will expect on june no no because they are telling actually even in the
01:43month of april itself but think that actually some because always some it is better to go to slow also
01:51because it is a mechanical part okay so far actually we completed 50 number of gates and then for
01:56remaining uh gates also material has is going to come back within two days and then uh uh within two
02:02months coming two months they will complete 100 percent 18 gates because we are uh manufacturing that is
02:08fabricating at one gathering unit and also here i think nine gates uh at one place another nine gates in
02:13a month in a spare of two months by it is it is not easy actually to reach the target so what do you say
02:19to farmers why is that because we are uh you know uh keen to complete within uh four to five months
02:25all the gates uh because as soon as the water will come on down uh because we are releasing to epg
02:34also extra power generation also releasing and then we will keep water at 43 tmc that means 1613
02:40level actually uh from that onwards so we'll because they had experience in uh uh doing uh farakka
02:46bearish and krishnash sagata and also even i think uh narenda 100 percent even will give within uh one
02:52one month also will keep a gap gap yes yes no doubt on because they told actually 10 gates but i am not
02:59telling to you 10 gates we eight gate only i'm telling in a month it is no because you are engineers no
03:08yeah no no okay let it be because you will report only we will do the work
03:12yeah yeah raghavendra raya sathya dharma arathaya cha bhajatam kalpurukhsha ya namatam kama dheno
03:18uh
03:21uh
03:23uh