00:00Bismillahirrahmanirrahim. Assalamu'alaikum warahmatullahi wabarakatuh.
00:05Regarding the investigation, the technical agencies involved in the investigation, PDRM, Bomber, Josh, KKR, and also Petronas,
00:20we are still in the process of stabilizing the land there to expose the pipes that are involved in the explosion and the fire.
00:34So to speed up this process, starting yesterday, we have taken two new actions.
00:41First, we added a generator involved in the excavation work.
00:47Second, we have been operating for 24 hours since yesterday.
00:51So starting yesterday, the cooperation work at the site will take place for 24 hours.
00:58Where the relevant technical agencies, PDRM, Josh, Bomber, JKR, JMG, and also JPS,
01:07will be present for a total of 24 hours to monitor and also analyze and investigate every level involved in the excavation work
01:19until the pipes that are involved in the explosion are exposed.
01:24Where the investigation time will be faster.
01:28Before this, I announced that we need two weeks for the initial report.
01:32But with these two new actions, the process will take place earlier than expected.