00:00CM Chandrababu has decided that the bypass to Amaravathi Rajadhani will reach Andhubad in June.
00:11The bypass from Kaja to Venkatapalem-Gollapudi and Chinnaoutapalli will reach Andhubad in June.
00:17Underpasses will be built along the four grid roads.
00:21Bypasses will not only reach Andhubad, Kerala, but will also facilitate the construction of the required equipment.
00:30The Kaja-Gollapudi package is 17.88 km from Kaja to Gollapudi and Chinnaoutapalli.
00:39It will cross nine grid roads in Rajadhani.
00:43NHAI has built underpasses where these 3, 8, 10, 13, and 15 grid roads cross.
00:53Bypasses have been built in these 9, 11, 12, and 14 grid roads without underpasses.
01:02That is, those four grid roads will be permanently closed in areas where bypasses cross.
01:08Those who do not cross these grid roads will have to take a different route to cross the bypass.
01:16The NHAI officials did not care about this matter.
01:22CM Chandrababu said that there should be underpasses after the Kootami government came into power.
01:29Engineers are working on the construction of underpasses by cutting the bypasses in those four places.
01:36CM also spoke to CM Nitin Gadkari.
01:39If the bypasses are cut and underpasses are built in those four places,
01:44it will take another 15 months to complete the first bypass.
01:50NHAI officials say that pending work will be completed by the end of June.