00:00The construction of the 4.76-kilometer Samal Island-Davao City Connector, or SIDC project,
00:07which was led by the Department of Public Works and Highways,
00:11according to the DPWH, reached 11.87 percent of the physical accomplishment of the project,
00:18which is far from being completed by September 2028.
00:21In the inspection carried out by the DPWH yesterday,
00:24the construction of the Pakiputan Strait and the land viaducts was explained.
00:28While also focusing on the safety of the workers
00:31and the ships passing around the active marine traffic areas.
00:35The project, which is worth P23.52 billion,
00:40was led by the Official Development Assistance,
00:43which includes a four-lane extradosed bridge,
00:47ramps, roundabouts, and marine and land viaducts.