00:00In Bogotá, the Autopista Norte can resemble a long line of stopped vehicles.
00:05Traffic jams are recurring on one of the main access roads to the capital, used by those who travel
00:10They come from the municipalities of La Sabana. The promise to expand it has been going on for years, amidst announcements and bureaucratic procedures.
00:15and environmental discussions. The National Infrastructure Agency and the Ruta Concessionaire
00:20Bogotá-Norte convened a new event on November 20th to kick off construction work on the street
00:26245 with presidential participation. However, the project already had a first important date,
00:32on April 6, when the start of the construction phase was signed, and another announcement on the 15th
00:37of
00:37October, when the district announced that work was beginning in this same area. What difference?
00:43To understand these three milestones? To understand it, we must reconstruct a story that began several
00:48years ago. The North Access 2 project was awarded in March 2022, but the road to
00:54The works encountered one of their main obstacles in January 2024, when the Authority
01:00The National Environmental Licensing Authority archived the first license application. The agency had
01:05insufficient information found to determine the environmental viability of the intervention,
01:10especially regarding its effects on the hydraulic and ecological connection of the Torca wetlands
01:15and Guaymaral. After new studies and an evaluation that included citizen participation, the Authority
01:21The National Environmental Licensing Authority granted the license in January 2026. In August, the
01:27The authority declared that an additional condition necessary to intervene in the strip had been met.
01:31among the wetlands. The signing of the agreement and the public announcements do not mean that everyone
01:37The new lanes are already under construction. On October 16, one day after the announcement
01:41The mayor's office reported that the ANI (National Infrastructure Agency) stated that preliminary activities such as plant rescue were underway.
01:47and wildlife management. These activities are part of the preparation for the project. However,
01:52Its presence alone does not allow us to establish how far construction has progressed or whether it is
01:57adhering to the contractual schedule. There is one difficulty that explains a good part of the setbacks.
02:02of this project. The northern highway crosses the area of two wetlands that exchange water
02:07and allow the movement of different species. According to the National Environmental Licensing Authority,
02:13Widening and raising the road without adequate measures could reinforce a barrier effect and disrupt the
02:18dynamics of flooding. Therefore, the concessionaire must implement hydraulic measures.
02:23Temporary measures that do not worsen existing conditions. Definitive hydrogeomorphological restoration.
02:29The wetlands, on the other hand, are the responsibility of FIDE and Comiso Lagos de Torca, in coordination with the
02:34The Bogotá Aqueduct and other district entities. They have different responsibilities, but their results are the same.
02:40They will need to be coordinated. The planned expansion includes the northern highway corridor.
02:44between 191st and 245th streets with new lanes, grade-separated U-turns, and pedestrian infrastructure
02:52and bike paths. It is part of Accesos Norte 2, which also includes interventions in the
02:57Seventh Avenue and the Sopo perimeter road. But the construction must meet other conditions,
03:03These include maintaining mobility during the works and executing the hydraulic structures.
03:08and allow the passage of wildlife between nearby ecosystems. The ANI estimates that the overall project
03:13It will be built by the end of 2031. Until then, the expansion will have to demonstrate that the
03:18Engineering and environmental protection commitments can be met on-site.
03:23After years of difficulties, the northern highway has an environmental license, a phase
03:27Construction had formally begun and there were several announcements about the start of work. But the decisive challenge
03:33The next step is to build the new lanes, meet environmental obligations, and respond.
03:38to the problems that justified the project. Because for those who travel this highway, everyone
03:43In the coming days, the result will not be measured by the opening ceremonies, but by the works that
03:48finally become operational.