Maharashtra halts Adani Energy's Tarali hydropower project citing forest act violations and lack of wildlife board approval.

Category

🗞
News
Transcript
00:00To another piece of breaking news and it's coming in this time from Mumbai where a major move has been
00:07taken by the Maharashtra Forest Department.
00:11A stop work notice has been issued to Adani Energy One Limited over the Tarali project, a hydropower project for
00:20alleged violation of the Forest Act.
00:23A letter issued by the Maharashtra Forest Department states that work on the project has commenced at Mauje Tarale, which
00:31falls in the deemed eco-sensitive zone of Sayadri Tiger Reserve near Satara.
00:35An inspection found that the actual execution of the project has started without obtaining the mandatory prior approval of the
00:44National Board for Wildlife.
00:46This is described as extremely serious and a violation of the prevailing Forest and Wildlife Acts.
00:51On another note, remember there was an Indian Express report last week which suggested that the project cost had been
00:57brought down to substantially.
01:00And as a result, there were questions being raised over the manner in which this project has taken place.
01:07The Adanis, of course, have rejected these allegations that have been made against them.
01:12But that major move has come in from the Maharashtra Forest Department.
01:16Joining me now is Mustafa Sheikh with the very latest on that.
01:20Mustafa, tell us more.
01:22It's not often that you see a project of the Adanis in a state like Maharashtra being issued a stop
01:29work notice.
01:29What more are you picking up?
01:31It's true, Rajdeep, that first the initial report suggested that the amounts were drastically brought down for the project, which
01:39is 99% of the amount was cut.
01:41Now, interestingly, Adani Energy Limited had issued a statement, one was regarding that the cost, which is 56 crores, is
01:49not the entire project cost, but the scope of work cost.
01:52But at the same time, they had said that this project doesn't fall in any forest area or ecologically sensitive
01:59zone.
02:00But the forest department, which has issued the stop work, have clearly mentioned that this project is in the eco
02:06sensitive zone.
02:07And the work had already started before getting the prior approval and needed permission.
02:12So that is one thing which the forest department has done a crackdown on the Adani Energy saying that rules
02:20were not followed and stop work has been given.
02:22Local are telling us that the work has been stopped and they are waiting for the report which was asked
02:26by the Ministry of Environment.
02:28Back to you.
02:29Okay, Mustafa, Sheikh, we'll wait and see what next the Adani group does and whether there is an attempt made
02:35to get the project back on track.
02:37Questions over that hydropower project in Maharashtra.
02:40Remember, the Adani group is rejecting the allegations, but that has not stopped the Maharashtra Forest Department from issuing the
02:47stop work notice.