Skip to playerSkip to main content
  • 3 months ago
Beneath the turbid waters of the Yangtze estuary, facing a cascade of challenges—complex hydrology, compacted sediment, and typhoons—the Chinese archaeological and salvage team broke new ground with the “Arc-shaped Beam Non-contact Integral Relocation Technique for Cultural Relics,” racing against time and wrestling with wind and waves. From design verification to construction under extreme conditions, every step embodied wisdom and courage. When the end-plate and longitudinal beam assembly was finally lowered to the designed depth, a dialogue across time and space began.

Category

🗞
News
Transcript
00:18In the turbid depths of the Yangtze River estuary, a Qing Dynasty merchant ship was discovered.
00:24It had rested there for more than a century. Confronted with such a massive and ancient wooden vessel, experts carefully
00:33considered which underwater archaeological and conservation plans to adopt.
00:38Underwater archaeology generally employs four methods.
00:42In-situ conservation is ideal for sites with stable environments, such as the Shengbei Yu Yuan Dynasty shipwreck.
00:50A cofferdam excavation method was successfully carried out at the Jiangkochenyin historic site in Sichuan province.
00:59Sectional recovery is often used for severely damaged shipwrecks, for example, the Huaguang Reef No. 1 Southern Song Dynasty shipwreck.
01:08However, these three approaches would still face major challenges in the Yangtze River estuary, leaving one final option.
01:20After much evaluation, it was decided that overall salvage would best preserve the historical information held within this ancient ship.
01:29The successful salvage of the Song Dynasty shipwreck, Nanhai-1, back in 2007, offered valuable experience and insight for the
01:38salvage project.
01:39However, the Yangtze River estuary No. 2 was larger and its environment more complex.
02:06After more than a year of comparative evaluation, a solution was found.
02:10Non-contact overall relocation of cultural relics using arched beams.
02:18How to make all the engineers and all the scientists believe that this project is possible.
02:27I think this is the most difficult thing, because its development is too big.
02:31The pioneering scheme employed a new generation of salvage technology.
02:37Engineers first sank an end plate and the longitudinal beam down to the riverbed.
02:43A launching frame was then installed, driving 22 giant arched beams to rotate and pass beneath the wreck.
02:51This technology innovatively drew on the tunneling shield excavation techniques,
02:57resolving the difficulties of threading steel beams encountered during the Nanhai-1 project.
03:03After the ancient ship and surrounding silt were fully encapsulated, the entire structure was lifted out of the water.
03:11Could this solution, embodying Chinese ingenuity, really overcome the formidable waters of the Yangtze River estuary?
03:40Hu Jian, diving team leader at Shanghai Salvage, also oversaw the Yangtze River estuary No. 2 salvage project.
03:48The approaching typhoon season only added to his stress.
03:54An assistant, Wang Yu, is the first female engineer from Shanghai Salvage to participate in an offshore construction project.
04:04After more than 50 consecutive days of effort from the team, side end plates and four longitudinal beams were successfully
04:12completed.
04:14Standing by was the main force behind this salvage operation, the Dali.
04:22This self-propelled floating crane has a lifting capacity of up to 2,500 tons.
04:30With a boom force reaching 6,000 tons, it can achieve remarkable feats in major engineering projects, as well as
04:38emergency salvage missions.
04:39From the
05:06However, with all preparations complete and offshore operations about to commence,
05:11a typhoon struck the region at the end of August.
05:15Work was brought to a halt as all personnel remained on standby, waiting for the storm to pass.
05:22Mid-autumn astronomical high tide arrived after the typhoon,
05:26causing the optimal window for offshore operations during this minor flood season to be missed.
05:33Typhoons are frequent in Shanghai during this season,
05:36so the large construction team couldn't afford to wait any longer.
05:44On September 6, 2022, after four hours in transit,
05:50the Dali arrived at the ancient shipwreck site, ready to drop anchor for positioning.
05:56Let's go.
06:02Engineer Yu Xiaogang from the Tianjin Research Institute for Water Transport Engineering
06:08utilized a differential global positioning system.
06:12It was capable of monitoring the relative position between the Dali and the ancient ship in real time,
06:18with an error margin of less than 10 centimeters.
06:31The primary task during this offshore operation was to place the end plates and longitudinal beams in their designated positions,
06:39a process that took more than seven continuous days.
06:44Yu Xiaogang and his colleagues also utilized pressure sensors and fiber optic technology
06:49to monitor the structure's underwater position and its depth in the sediment.
06:54This formed the core framework of the arched beam system.
06:59It had to be precisely positioned to ensure the smooth execution of subsequent operational stages.
07:07The Dali performed fine adjustments by altering the lengths of its anchor cables.
07:13The giant crane carefully lowered parts while ensuring that the four guide sleeves were aligned with the positioning piles.
07:25Technicians carefully monitored the entire process from start to finish.
07:34As the end plates neared the seabed, the chain bucket mud removal device was activated.
07:40This excavated silt and lifted it above the end plates.
07:44After being pulverized by a high-pressure water pump spray, silt was carried away by the water flow.
07:51The end plates sank naturally under their own weight.
08:00Zhuang Xianwei, deputy chief engineer of the mechanical manufacturing branch of Shanghai Tunnel Engineering,
08:07was responsible for the design and construction of this arched beam system.
08:12All automated equipment operations were centralized in this control room.
08:22Inside the control room, spirits were high.
08:26Monitoring data indicated that everything was proceeding smoothly, putting the project ahead of schedule.
08:33The forecast was 24 hours.
08:36But in the actual operation, the speed was quite fast.
08:41The forecast was about 5-6 hours.
08:46With everyone welcoming the smooth progress, monitoring data began exhibiting anomalies.
08:54The structure s depth in the sediment showed increasing deviations.
08:59Its inclination angle quickly exceeded the design parameters.
09:17No one could predict the underwater conditions for certain.
09:22A diver needed to be sent down to confirm the specifics.
09:26Everyone was anxiously awaiting the arrival of slack tide.
09:50Finally, a diver could enter the water.
10:11On site investigation revealed that the positioning piles on the north side were pressed tightly against the stiffened plates in
10:19the inner walls of the pile casings.
10:21The entire combination has shifted slightly to the south.
10:26Analysis indicated that this resulted from the two northern positioning piles slightly tilting southeast during placement.
10:35Although this deviation was within the design's tolerance, the gap between the northern positioning piles and the casings progressively narrowed
10:44as the end plates were lowered.
10:45Unable to push away the thick and sticky silt nearby, the end plates jammed.
10:54In response to this emergency, Hu Jian promptly gathered the team to discuss possible solutions.
11:00The
11:01Now we're planning to take the machine to cut the machine out of the machine.
11:05It's just three or four.
11:07It's only two.
11:09I'll ask you, if I cut it out after I put it, it will not be able to cut it
11:12again.
11:13It's not going to be able to cut it again.
11:17We'll have some new problems.
11:18Together, we'll have a lot of problems.
11:25We'll have a lot of problems.
11:27We'll have a lot of problems.
11:38The generous gap inside the pile casings created by the stiffened plate structure during an initial
11:44stage was put to good use. The structure was hoisted out of the water. Workers promptly
11:54cut off the stiffened plates inside the four pile casings to enlarge the openings. Hoping
12:00to prevent the end plates from shifting southward again, two sets of guide rollers were installed
12:05inside the pile casings on the south side. This forced the end plates to move northward.
12:12On the exterior of each pile casing, three temporary L-shaped stiffened plates were installed
12:18to ensure precise positioning. If necessary, underwater trimming could later be carried
12:24out. Intense alterations continued throughout the night.
12:32On the afternoon of September 9th, 2022, the structure was lowered for the second time.
13:15before long, the structure had successfully been lowered to a suitable depth.
13:26However, the additional task of cutting the stiffened plates underwater still added to the
13:32diver's workload. Their already tight operation schedule was becoming even tighter.
13:40water needed to change. The air is a huge impact of the air. If we're too fast, then we couldn't
13:44land. If the air is too fast, then we can't land until we land. It can't land until it
13:50in place. The air is to land, if it is at the에요. The air is empty, then we don't land
13:53until
13:53there. Then we have to have a quick week until we start to develop. Then we have to wait until
13:54the
13:54sea of wind is slow. As we're early in the day, there's 4-day Nico Bodet.
13:56We have four cases. Every second counted. Missing slack tide would mean waiting hours more.
14:17To enhance underwater operational efficiency and ensure diver safety, Shanghai Salvage
14:24urgently dispatched the workboat to support the Dali.
14:27In doing so, the number of divers working rose to four.
15:15The jamming issue between the positioning piles and their casings was resolved, yet Hu Jian still grew increasingly worried.
15:36The 12th powerful typhoon of 2022, Meihua, formed over the northwest Pacific Ocean on September 8th.
15:45It was expected to approach the Zhejiang coast on September 12th and continue moving northward.
15:52This meant that the Dali had to be withdrawn from the site by September 13th, at the very latest.
15:59With less than 96 hours remaining, could the Dali complete its mission before the typhoon struck?
16:07Offshore operations continued around the clock.
16:10There was absolutely no time for delay.
16:13Within one metre of the structure's target depth, another problem emerged.
16:21...
16:22...
16:22.
16:51This sandbar at the Yangtze
16:54River estuary is a submerged shoal, notorious among local fishermen. It's also known as the
17:00iron plate bar. The hardened underwater shoal was formed by the unique mix of brackish and
17:06fresh water along with continual sediment deposits in the estuary.
17:26Sinking the end plate was facing unprecedented challenges. Hu Jian decided to implement a
17:32backup plan. To address situations like this, eight sets of suction pipes were pre-installed
17:38inside each end plate. Divers carrying water sprays entered the end plate cavity to disperse sediment,
17:45helping it sink. Inevitably, the mid-autumn tide soon arrived. This made diving conditions
17:58even more challenging.
18:16Sinking.
18:44Sinking twenties in the dangerous
18:47Go ahead.
18:48Right.
18:49Right.
18:50What's the case?
18:51Go ahead.
18:52Go ahead.
18:53Go ahead.
18:54Go ahead.
18:56Go ahead.
18:57Go ahead.
18:57Go ahead.
18:59I'm going to move over.
19:00I'm going to go ahead.
19:01I'm going to move over.
19:05I've got the back-up plan to show you success.
19:09The south end plate was practically settled into the desired position, but the north end
19:14plate wasn't quite there yet.
19:39The typhoon was closing in, time was running out.
20:07After accounting for necessary withdrawal time, less than 24 hours remained to lower the end plate.
20:38To overcome this final hurdle, Hu Jian's team made a bold decision.
20:44Suspending mud removal operations on the south side while unloading the lifting hook of crane number one, they added nearly
20:52200 tons of weight to the end plate.
20:55By harnessing the force of natural subsidence, they aimed to remove their final obstacle.
21:18At 3am, on September 12th, 2022, underwater probing finally delivered some good news.
21:27The structure was successfully positioned at the designed depth.
21:31The requirements for the launching frame installation and arched beam threading had been met.
21:48In the face of nature, the mind of the world is the most important part of the world.
21:49The world is the most important part of the world.
22:00in the face of nature the marvels of human engineering often appear insignificant it is
22:11precisely this pressure this race against time and struggle against the elements that brings
22:17greater significance to each breakthrough successfully sinking the end plate was not
22:24only a technical triumph but also a testament to the strength of this team in extreme conditions
22:31after typhoon mehua swept through the area the waters soon calmed once again the next chapter
22:39of this legend was ready to be written in the depths of these waters as other questions waited to be
22:45answered

Recommended