ଭାରତ ସରକାରଙ୍କ ଭାରତମାଲା କରିଡ଼ର ଅନ୍ତର୍ଗତ ପ୍ରକଳ୍ପରେ ଓଡ଼ିଶାରେ 2ଟି ଟନେଲର ନିର୍ମାଣ କରାଯାଇଛି । 2027ର ପ୍ରଥମାର୍ଦ୍ଧରେ କରିଡର ଯାନବାହାନ ଯାତାୟାତ ପାଇଁ ଖୋଲାଯାଇପାରେ ବୋଲି ଅଧିକାରୀ କହିଛନ୍ତି ।

Category

🗞
News
Transcript
00:00foreign
00:10the project od7 4 km is a 3.4 km tunnel
00:14this is the first tunnel and it is made by many new techniques
00:20this is a 500-600 people in this way
00:24we have developed skill development for local employment
00:29the electrician, fitter, operators
00:31which was the ordinary society
00:33we have trained and deployed here
00:36and the project in the future
00:40for tourist attractions
00:41we have two portals
00:44on the two corners
00:46we have placed a village
00:47and on the other side
00:49we have placed a facade
00:51which will attract tourists
00:54and will boost the culture and heritage
00:56in Odisha region
00:56we have placed a safe man-hours
01:01a good thing is that
01:02all of these tunnels
01:04are designed to make in india
01:05and their quality is a European standard
01:09we have achieved 36.8 million safe man-hours
01:14this means that
01:15if someone has achieved 36.8 million man-hours
01:18it is a remarkable achievement
01:22total three tunnels are there
01:23Chhattisgarh one tunnel around 3 km
01:25and Odisha
01:26first time six lane tunnels are 3.43 km
01:30second tunnel 2.93 km
01:32so these
01:33what are the security measures we are taking?
01:35yes sir
01:36complete highway
01:37advanced traffic management system
01:39first time in Odisha we are providing
01:41every km
01:41one camera is provided
01:43it is controlled with the control room
01:45central control room
01:46so that
01:47all vehicles
01:49whatever travelling on the highway
01:50we are capturing
01:51every 10 km
01:52we are providing the speed detection camera
01:55and the highway also
01:56inside tunnel
01:57every 200m we provided cameras
02:00and firefighting system
02:02ventilation fans
02:03jet fans are provided
02:04as per the international standards
02:05and complete S.Y.S. facilities are provided
02:09and six cross passages are provided
02:11from one side
02:12one tunnel to the other tunnel also
02:14in case of accidents
02:15and in case of emergency
02:17we can shift to the other tunnel
02:19and safely we are evacuating
02:20ambulance, cranes, petrolling vehicles
02:23are provided all around the highway
02:24sir we are expecting for
02:26Kaurapur portion by June 2026
02:29already Naurangpur completed
02:30Andhra side they are expecting
02:32full completion by August-September
03:03Naurangpur