00:00The Bureau of Internal Revenue, or BIR, has now filed 13 criminal complaints related to anomalies in flood control projects.
00:08The latest one lodged today with the Department of Justice was against the sole proprietor of Wawaw Builders.
00:15The contractor is allegedly involved in a ghost flood control project in Malolos City, Bulacan,
00:21and is facing a tax liability amounting to 48.39 million pesos.
00:27According to BIR records, Wawaw Builders was awarded a 77.20 million pesos contract for a riverbank protection structure in Barangay Kaingin.
00:38However, verification by the BIR and the Commission on Audit revealed that no structure was found at the project site,
00:46despite the company declaring 100% project completion.
00:49According to BIR Commissioner Charlito Martin Mendoza,
00:54the agency's investigation and filing of cases will continue against contractors who abuse public funds and fail to pay the correct taxes.