00:00Three important projects have been launched today.
00:04One is the Sanchar Sathi mobile app.
00:07It is a supporting app for our customers to experience a secure telecommunication facility.
00:19He has launched that.
00:21The second project is the Intra-Circle roaming, where mobile towers are installed based on the Digital Bharat Nidhi Fund without any coverage.
00:41The third project is National Broadband Mission 2.0.
00:47National Broadband Mission 2.0 aims to achieve more than what we have achieved so far.
00:57It aims to create customer centric telecommunication facilities.
01:08He has launched these three projects.
01:10The Minister has explained everything very well.
01:14The Sanchar Sathi mobile app is used to monitor fraud calls.
01:24The fraud calls are monitored through the Sanchar Sathi mobile app.
01:28Central Government takes the number of complaints and sends it to the concerned operator.
01:37The operator verifies the number and takes action to disconnect the number.
01:43This is one of the facilities in the Sanchar Sathi mobile app.
01:45If someone misuses your name and documents to get a connection, you can find it out yourself.
01:54If someone misuses your name and Aadhaar number to get a connection, you can find it out yourself.
02:03If you register that it is not the case, they will take action and disconnect the number.
02:09If your mobile phone is lost, you can register it in the Sanchar Sathi mobile app.
02:16No one will use your lost mobile phone.
02:22If someone tries to use it, they will locate it, retrieve it and give it to you.
02:29This is the third facility.
02:33If you buy a new mobile phone, you can find out if it is a genuine or a stolen one.
02:47If you register your IMEI number in the mobile app, they will show it to you.
02:52This is the fourth facility.
02:54If you receive any international fraud calls, you can register it and they will take action to disconnect the number.
03:03These are the facilities in the Sanchar Sathi mobile app.
03:08This was already available on the website.
03:10Since many people cannot access the website using a computer, they have made it available on mobile.
03:18This is the Sanchar Sathi mobile app.
03:20Next, I would like to talk about the intra-circle roaming.
03:23In some villages, there was no coverage in our country.
03:27The government decided to use the central government fund to provide coverage.
03:35They supported the establishment of the tower.
03:39They gave the funds to the BSNL and asked them to erect the tower.
03:45In Tamil Nadu, there are 223 such towers.
03:53This is a 4G saturation project.
03:58This is a make-in-India project.
04:06When the BSNL equipment was installed in these towers, only the BSNL customers could access the service.
04:18In other villages, when there is a connection with other operators like Jio, they do not receive the signal.
04:28They cannot speak from there.
04:30So, they made an agreement to install a roaming facility in these towers.
04:34They used the services provided by the BSNL and created a facility for them to call.
04:39This is called intra-circle roaming.
04:41Next is National Broadband Mission 2.0.
04:46They have fixed many targets in the country.
04:52The target is to provide 2.7 lakh villages.
04:5795% of these villages must be in working condition.
05:05The target is to provide 90% of these villages with broadband connectivity.
05:20The target is to increase the speed of the internet to 63 Mbps.
05:29The target is to increase the speed of the internet to 100 Mbps.
05:32The target is to provide optical fiber connectivity.
05:38The target is to provide optical fiber connectivity.
05:41The next target is to map all these targets in a national portal.
05:46If someone wants to create a telecom facility, they do not have to use their own fiber.
05:54They can use the existing fiber.
05:56This will reduce the capital cost of the project.
06:00They will be able to provide services at a lower tariff.
06:04Next is the ROW permission.
06:07If someone wants to connect a cable, they have to get permission from the state government and the corporation.
06:14In the past, the process was manual.
06:17They will give a letter, wait, and follow up.
06:20In the past, it took 300 to 400 days to get the approval.
06:24The central government brought the ROW rules.
06:27They fixed a 60-day timeline.
06:29They gave an application within 60 days.
06:32If there is no communication, they brought a concept called deemed approval.
06:36If the government does not respond, they will give the approval within 60 days.
06:41They brought the concept of deemed approval.
06:44Now, the target is to reduce the time by 30 days.
06:47They have brought this in National Broadband Mission 2.
06:50Next is the towers.
06:52Many towers work with EV supply.
06:55It is a conventional energy like solar.
06:58It is a non-renewable energy.
07:01The target is to connect 30% of the mobile towers with that energy.
07:07It is in NPM 2.0.
07:09There is an app called Call Before Dig.
07:12If you want to connect a cable to the road,
07:16it will disturb the infrastructure.
07:21If you connect it to someone else, the cable will be disturbed.
07:24If you connect it to a water or drainage connection, it will be disturbed.
07:29Whatever permission you get to work on the road,
07:33if you register through this app and say that you are going to start working on a certain date,
07:39the other cable agencies on the road will be alerted.
07:47This particular agency is going to appear on this particular date.
07:52Immediately, the agency will coordinate with them
07:56and tell them where the cable is and tell them to dig it.
08:02The infrastructure below will be protected without any damage.
08:07This is an important app.
08:10If you use this app on any infrastructure,
08:13there will be no damage or disturbance.
08:16There will be no disturbance to the services of the people.
08:19The next target is to fully roll out the 5G network.
08:27Power companies are using overhead optical fiber.
08:33They are using it only for their communication.
08:38Sunil Govt. has brought the fiber so that other operators can benefit from it.
08:45This is a salient feature.
08:48It will be in many NBM documents.
08:50It has just been released today.
08:52We will share the document in the mail.
08:54These are the three documents that our Minister has launched.
08:58In Tamil Nadu statistics,
09:01there are 223 villages with towers in Digital Bharat Nidhi.
09:09197 sites have already been commissioned.
09:13Only 26 sites are pending.
09:1618 sites will be commissioned by March.
09:20There is a separate rule for forest permissions.
09:26There is a delay because we have to follow it.
09:28Apart from those 8 sites,
09:30all the sites will be commissioned by March 31.