00:00The protection of the residents of Araya and Pampanga will serve to fight the flood
00:10with this slope protection or retaining wall on the side of the river.
00:16It's worth almost Php 100 million.
00:22But it hasn't been a year since this was done.
00:27Why did the flood control project suddenly stop?
00:34It's not familiar. It's dangerous.
00:38Because the wall is broken.
00:41I don't know.
00:42There's a lot of metal in the water.
00:45And there's a crack.
00:47I don't know if it will work.
00:54That's why the residents living on the side of the river
00:59had to flee because of the flood.
01:02I don't know.
01:05Where are you going? It's dangerous.
01:10The flood is coming.
01:12We are calling for help.
01:14God is with us.
01:16People are drowning.
01:18It's very dangerous.
01:22Why did you design this?
01:29This project is a waste.
01:34It's a waste of money.
01:37This retaining wall is 100 meters long.
01:40It was built so that the flood won't reach the town of Araya
01:43when the water level in the river rises.
01:46But after more than a year,
01:48this part of the retaining wall has already collapsed.
01:53In the town of Licab, Nueva Ecija,
01:56a flood control project was also destroyed
01:58in the aftermath of the Super Typhoon Pepitong.
02:05It's worth more than 47 million pesos.
02:10Because of the destruction of the project,
02:12the entire town was flooded
02:14and some farmers lost their livelihood.
02:17This part was destroyed
02:20and all the water came to us.
02:29Every project was spent by the town.
02:34That's why we should investigate
02:38and ask,
02:40where is the money?
02:52Mom, I'm hungry.
02:57Yesterday, August 16, 2024,
02:59residents of Barangay Cantading, Araya, and Pampanga
03:03were forced to leave their homes
03:05when the land next to the river suddenly split
03:08after the rain.
03:11It's so bad.
03:14It's worse than this.
03:17It's even worse than this.
03:19It was destroyed.
03:24Because Pampanga is considered a catch basin,
03:29the Department of Public Works and Highways
03:33or DPWH built a slope protection
03:35or retaining wall project.
03:40This will serve as protection for the residents
03:43and the community whenever the water level rises
03:45in the Pampanga River.
03:49But on the morning of August 17,
03:51the land split even bigger
03:54and the retaining wall was destroyed.
04:00Guys, there's a fire here.
04:02It's burning.
04:06There's a fire here.
04:08It's dangerous.
04:10There's a fire here.
04:15It's deep here.
04:17There's a hole here.
04:19There's a crack here.
04:21It's a crack.
04:23I'm sure it will explode.
04:27I don't know.
04:30Because of the earthquake,
04:32the land around the destroyed project
04:34is almost completely destroyed.
04:37Even the houses are destroyed.
04:39Come here.
04:41It's dangerous.
04:43There's a fire here.
04:46We're calling you.
04:48God is with you.
04:50There's a fire here.
04:52It's dangerous.
04:55The resident, Marcos Castillo,
04:57noticed the land splitting
04:59and the landslides
05:01in their area.
05:03At first,
05:05it was like half a meter per day.
05:07The next day,
05:09it was one meter.
05:11Now, it's three meters.
05:15It's deep.
05:17But one night,
05:19he heard a loud explosion.
05:22The project was already under construction.
05:30That's where the concrete
05:32and the steel
05:34is splitting.
05:36That's where it's splitting.
05:38When we woke up,
05:40we noticed
05:42that the land was falling.
05:44The land was slowly falling.
05:47When the retaining wall was built,
05:49his house collapsed
05:51and almost nothing was left.
05:55This is my house.
05:57That's the kitchen
05:59and the room.
06:01Half of the room fell.
06:03Can I sleep here?
06:05Of course,
06:07I can't.
06:09I have to take care of it.
06:11It's very heavy.
06:13I grew up here
06:15with my family.
06:17I won't just leave
06:19this land.
06:23In the document obtained
06:25by the Reporter's Notebook
06:27from DPWH,
06:29the retaining wall is worth
06:31Php 91.6 million.
06:33In February 2023,
06:35DPWH started the project
06:37Flood Management Program
06:39Rehabilitation of Flood Mitigation Facilities
06:41within Major River Basins.
06:45It was declared 100% completed
06:47in October 2023.
06:51The General Appropriations Act
06:53or GAA,
06:55or Kaban ng Bayan,
06:57had no funds.
06:59But less than a year later,
07:01the project started.
07:05On August 19,
07:07two days after the project started,
07:09the Reporter's Notebook
07:11went to the project.
07:15This retaining wall
07:17is 100 meters long.
07:19It was built
07:21so that it won't flood
07:23the town of Arayat
07:25when the water rises
07:27in the river.
07:29The construction started
07:31in February 2023,
07:33but after more than a year,
07:35this part of the retaining wall
07:37has already collapsed.
07:39We were lucky that the contractor
07:41was able to repair
07:44What are you restoring now?
07:46Did you know?
07:48Have you taken into consideration
07:50that it could flood again
07:52because the land will move?
07:54Actually, we already put
07:56a water basin outside.
07:58We put big debris
08:00so that it won't flood.
08:02The land here is already
08:04damaged.
08:06This project is 107 meters long.
08:08In the flood,
08:1050 meters were damaged
08:13The contractor explained that
08:15they just followed the design
08:17given by the DPWH.
08:19What did the DPWH say
08:21about the design?
08:23Yes, because that's what
08:25they do in other projects.
08:27That's what we did.
08:31But in the design,
08:33did they say that
08:35the land could move?
08:37No.
08:39Why don't you know?
08:41If this retaining wall is built,
08:43it will cost almost P100 million.
08:45Why don't you know
08:47that it will happen?
08:49Shouldn't you have studied it?
08:51We didn't study it.
08:53So it's a waste.
08:55This project is a waste.
08:57That's why we're doing
08:59a restoration.
09:01Reporters Notebook went to
09:03the office of DPWH Region 3
09:05to find out why
09:07the P100 million project
09:09was affected.
09:11The affected area
09:13of our project
09:15is where the
09:17embankment was settled.
09:19Then our sheet piles
09:21tilted
09:23towards the river.
09:25There are dead man
09:27or anchors there.
09:29You can see that
09:31they really
09:33resisted.
09:35But because of the
09:37weight of the water,
09:39or the soil
09:41underneath.
09:43According to DPWH,
09:45before the project was implemented
09:47and started,
09:49their agency will be blamed.
09:51Of course, there will be a survey
09:53and a plan will be made.
09:55But before the plan is made,
09:57there will be an investigation.
09:59Like the soil,
10:01the water,
10:03the topography of the
10:05location of the project
10:07that you want to do.
10:09After the
10:11construction of the project,
10:13they promised to continue
10:15monitoring the contractors
10:17in its repair.
10:19Accordingly, our contractors
10:21are repairing.
10:23We are monitoring them.
10:25The government will not spend
10:27anything because the project
10:29is under warranty.
10:31But in the middle of
10:33the repair of the retaining wall,
10:35the other parts of the project
10:37fell again
10:39because of the storm.
10:45In this video,
10:47you can see that
10:49the damaged part of the project
10:51almost sank because of the water.
11:03The reporter's notebook
11:05brought the location back.
11:07The old
11:09dented retaining wall
11:11completely collapsed
11:13and almost fell into the river.
11:21The residents living
11:23around it were more scared.
11:25Of course, we were scared.
11:27Is that Christine?
11:29The one who saved us?
11:32It collapsed.
11:34It was like it exploded.
11:36And when the flood came,
11:38it didn't last long
11:40because the houses fell.
11:44Three months after the collapse
11:46of the retaining wall,
11:48this is what the house of Marcos looks like now.
11:52Their kitchen and room
11:54completely collapsed.
11:56The ground was sinking
11:58until it fell
12:00into the house.
12:02There's still a little bit left.
12:06The couple decided
12:08to temporarily leave the place.
12:12Of course, I'm worried
12:14especially because
12:16we're just staying here.
12:18It's a different feeling
12:20to be at home.
12:22I'm waiting for it to end
12:24so that we can come back here.
12:26We again interviewed
12:28VPWH Region 3.
12:30You've mentioned before, sir,
12:32that you will monitor
12:34the ongoing repair.
12:36But sir, what happened?
12:38Why did that project
12:40collapse again?
12:42The problem is
12:44when the water comes,
12:46like for example,
12:48the potato, when the water rises,
12:50we can't do the repair.
12:52So mostly, when it falls,
12:54that's when we do the repair.
12:56We do it quickly
12:58to protect
13:00the people.
13:04We showed an expert
13:06the damaged part of the retaining wall.
13:08According to him,
13:10the sheet pile can really be used.
13:12It's an appropriate material as a slope protection.
13:14The question is, is the design right?
13:16The thickness of the steel used,
13:18the layout,
13:20the depth that penetrates
13:22inside. The way I look at this,
13:24from this point of view,
13:26this should be protected.
13:28It's also important
13:30to re-study the design
13:32before doing the project again.
13:34Review the previous design
13:36which failed
13:38and involve the other DC team.
13:40It shouldn't have
13:42a failure if the
13:44design considerations are correct.
13:48There's an additional design there.
13:50It's a suggestion to put
13:52corrugated pipes.
13:54There are holes
13:56at the bottom
13:58so that the softening
14:00of the soil
14:02can be avoided.
14:06The work there is amazing.
14:08If you look at it now,
14:10we're within
14:1240%
14:14of completion.
14:18They also assure that
14:20the funds will be used
14:22to rebuild the damaged part of the retaining wall.
14:24It's an underwater type.
14:26That's why
14:28we're using it
14:30as a fund
14:32taking into consideration
14:34all the
14:36things that happened there.
14:40In the town of Dikab de Vaisiha,
14:42a flood control project
14:44was built by DPWH.
14:46It's considered
14:48a catch basin
14:50in Nueva Ecijang, Ilikab.
14:52But one part
14:54of the flood control project
14:56was damaged
14:58by a typhoon.
15:02In the document obtained
15:04by the reporter's notebook from DPWH,
15:06the project started in February
15:08and ended in Marito in June 2020.
15:10It's worth
15:12more than P47 million.
15:16This was obtained by residents
15:18in Nueva Ecija, Ilikab.
15:20You can see here
15:22the taste of the super typhoon Pipito.
15:26That's where
15:28the impact of the water was.
15:30The water from
15:32that river came here.
15:34It directly reached
15:36our crops
15:38like eggplant, vegetables,
15:40corn, and rice.
15:42The crops of
15:44Simang Jose Padrones
15:46were destroyed
15:48by the flood.
15:50We didn't expect
15:52the flood to come here.
15:56What we fear
15:58is the typhoon.
16:00In the early morning,
16:02suddenly,
16:04the water
16:06was flowing
16:08to our fields.
16:10In the afternoon,
16:12suddenly,
16:14our fields were saved.
16:16That's why
16:18in front of my field,
16:20in August,
16:22all of our crops were washed out.
16:24Only a few trees
16:26were left.
16:28Only a few trees were left.
16:30It's not good anymore.
16:34The biggest problem of Simang Jose
16:36is how to recover
16:38more than Php 50,000
16:40that was borrowed.
16:42We spent a lot
16:44to recover it.
16:46Then, everything was destroyed.
16:50Why was the project destroyed
16:52just 4 years ago?
16:54Our project is
16:56first of all,
16:58the rainfall
17:00or the water runoff
17:02from the Talavera River
17:04has a high volume.
17:06For the EPWH,
17:08we were not able to put
17:10a sheet pile
17:12on our slope protection
17:14because we did not expect
17:16that the water flow
17:18would be too high.
17:20The rainfall
17:22caused the damage.
17:24We have already
17:26requested funds
17:28for that.
17:30We are just waiting for the funds
17:32to be released so that we can rehabilitate the dike.
17:36Secretary,
17:38we cannot avoid
17:40the affected communities
17:42to think
17:44that these projects
17:46are substandard
17:48or have quality problems
17:50or the construction is not good.
17:52How would you address that, Secretary?
17:54What we are saying is
17:56that the design parameters
17:58were low
18:00to cope up with
18:02the climate change phenomenon.
18:04We are rehabilitating
18:06to make it stronger
18:08and we will be using
18:10new design standards.
18:14According to the EPWH,
18:16more than 5,500
18:18flood control projects
18:20were completed from 2022
18:22to 2024.
18:24The total funds spent
18:26on those projects
18:28amounted to more than
18:30Php 268 billion.
18:32The region 3 or
18:34central zone is the largest
18:36with more than 800 projects.
18:38More than 600
18:40flood control projects were built
18:42in the National Capital Region
18:44or NCR.
18:46More than 600 in Region 1
18:48or Ilocos Region.
18:50More than 400 projects in Region 2
18:52or Cagayan Valley.
18:54Region 4A or Calabar Zone.
18:56And Region 8 or
18:58Eastern Visayas.
19:00Let's go to Region 5
19:02or Bicol Region.
19:08Reporters also visited
19:10some flood control projects
19:12in NCR
19:14like the one located
19:16in Binondo, Manila.
19:18We were able to reach
19:20the two parts of the
19:22Flood Mitigation Facility
19:24in Estero de Binondo.
19:26This is where the garbage
19:28from the waterways
19:30is collected to avoid
19:32flooding.
19:34Despite the thousands
19:36of flood control projects,
19:38the number of floods
19:40in Region 3, NCR
19:42and Bicol Region
19:44is increasing.
19:46Flood control projects
19:48are still a viable option
19:50or it's high time
19:52to think of other options.
19:54We have to understand also
19:56that engineering intervention
19:58is just one of the solutions
20:00to mitigate flooding.
20:02I think we should
20:04help each other
20:06to avoid flooding
20:08problems.
20:10Environmental issues,
20:12urban areas,
20:14land use
20:16and
20:18waste management.
20:21The water level is really high.
20:23President Bongbong Marcos also asked
20:25why despite having
20:27a billion pesos worth
20:29of flood control projects,
20:31the number of floods
20:33in the country is still increasing.
20:35If you look at the statistics,
20:37in Baguio-Undoy,
20:39the water level dropped
20:41400 plus centimeters.
20:43Here in Cristin,
20:45the water level dropped
20:47about 700 plus centimeters.
20:49Almost twice that of Undoy.
20:51That's why the flood control
20:53projects were made
20:55for areas like Undoy.
20:57The time has really changed.
20:59Just this November 6,
21:01the Senate proposed
21:03a fund for
21:05flood control projects
21:07worth more than 500 billion pesos
21:09within 3 years.
21:11The budget of our government
21:13for flood control alone
21:15including DPWH,
21:17MMDA, Climate Change Commission,
21:19DENR, etc.
21:21is worth
21:231,444,000,000 pesos a day.
21:25So,
21:27we want to check and know
21:29where this is going to go.
21:33How is this going to change
21:35the time now?
21:37The floods are increasing.
21:39How are you preparing
21:41for such scenarios?
21:43We have to review the fundamentals
21:45on engineering
21:47designs.
21:49Maybe we will add
21:51our parameters
21:53to make our
21:55projects more
21:57resilient
21:59for the climate change phenomenon.
22:01If we are using
22:0325-30 years
22:05return period,
22:07maybe we will use
22:0950 years return period.
22:15Billions of pesos were spent
22:17for the government's
22:19flood control projects.
22:23But it is clear
22:25that some of them
22:27did not become effective
22:29so many drowned in the floods.
22:33Floods that cause
22:35damage to many households,
22:41damage to hectares of
22:43livelihoods,
22:45and are dangerous
22:47to the residents.
22:49Until next Saturday,
22:51I am Mackie Pulido.
22:53I am Jun Valeracion.
22:55And this is the Reporter's Notebook.